# Transformer and power converter: Use case

Source page: https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-use/

#### Use cases

Each use, its share of demand and volume, how critical the product is to it and why, and the price paid

| Use case | Volume | Unit | Criticality | Reason | Price | Price unit | Year | Source |
|---|---|---|---|---|---|---|---|---|
| Power transformers in substations and power stations | 113,013 | MVA of AC transformation capacity added in India in 2025-26 | Essential | No other device steps grid voltage up and down at this scale with losses below 0.4% (calculated for the 40 MVA unit). | 23.37 | INR crore per single-phase 500 MVA transformer (POWERGRID contract average, September 2026) | 2026 | ^[19]^[21] |
| Distribution transformers (pole and pad units) | 41 | % rise in US distribution transformer demand since 2019 | Essential | The last step down to 420 V has no alternative; every connected building depends on one. | – | – | 2025 | ^[8] |
| Solar farms and rooftop PV (inverters) | 589 | GWac of PV inverters shipped worldwide in 2024 | Essential | Solar panels make direct current; an inverter is needed to feed the alternating-current grid. | – | – | 2024 | ^[10] |
| Motor drives (variable speed inverters) | – | – | Important | A motor can run without a drive, but it then cannot adjust its speed; ABB's 7.5 kW drive is designed for 15 years of 5,000 hours a year. | – | – | 2008 | ^[6] |

as of 2026-11-13

#### Industries that buy it

The industries and kinds of firm that buy it, for which use case, and how critical it is to them
 Used by

- [Utilities, transmission companies and renewables developers](https://www.materialinsights.org/industries/electrical_equipment/) Substations, distribution networks and solar farms · criticality essential Utilities, transmission companies and renewable developers buy power and distribution transformers and inverters; in India POWERGRID is one buyer ^[21].
- [Substation and transmission EPC contractors](https://www.materialinsights.org/industries/electrical_equipment/) Substation construction · criticality essential Substation and transmission contractors specify and install the units.

as of 2026-11-13

#### How it is used

Lifetime, use per year and utilisation, by variant

| Measure | Value | Unit | Variant | Place | Year | Source |
|---|---|---|---|---|---|---|
| Reference service life of the Indian 400 kVA transformer | 35 | years | Distribution transformer | India | 2026 | ^[2] |
| Reference service life of the 40 MVA transformer | 35 | years | Power transformer | World | 2025 | ^[3] |
| Average load assumed by the ABB 40 MVA declaration of 2003 (newer declarations ^[1]^[3] use 70%) | 50 | % of nominal power | Power transformer | World | 2003 | ^[4]^[1]^[3] |
| Suggested lifespan of a large power transformer, against an average installed age of 38 to 40 years | 25 | years (upper end of 20 to 25) | Power transformer | United States of America | 2022 | ^[7] |
| Reference service life of the inverter in its declaration | 25 | years | Inverter | World | 2023 | ^[5] |
| Inverter life of 10 to 15 years, quoted by the JRC preparatory study from an IEA PVPS report, in its discussion of failure statistics | 15 | years (upper end of 10 to 15) | Inverter | World | 2018 | ^[25] |

as of 2026-11-13

#### Prices

Unit prices by market or use, with year and source

| Market | Value | Unit | Year | Source |
|---|---|---|---|---|
| 500 MVA, 765/400/33 kV single-phase transformer, POWERGRID contract with CG Power, average | 23.37 | INR crore per transformer | 2026 | ^[21] |
| 25 MVA transformer, Maharashtra utility (MahaTransco) schedule of rates | 3.68 | INR crore per transformer | 2026 | ^[21] |
| Power transformer prices, rise since 2019 reported by the IEA | 75 | % rise since 2019 (around) | 2025 | ^[9] |

as of 2026-11-13

#### Sources

1. [Liquid immersed distribution transformers with 400 kVA operating power (EPD-SE_DB-003, EPDITALY0263, issued 31 March 2022, updated 9 October 2025)](https://www.epditaly.it/en/wp-content/uploads/2016/12/EPD0263_SE_DB_003_400kVA-09-10-2025.pdf) Siemens Energy Distribution Transformers Kft., registered with EPDItaly, 2025, GWP table, unit 9141275628
2. [Environmental Product Declaration: TR-400 kVA Transformer, models 110081 and 110169 (EPDITALY1233)](https://www.epditaly.it/wp-content/uploads/2016/12/Vijai-Electrical_EPD_Transformer-Products_26012026.pdf) Vijai Electricals Ltd (India), registered with EPDItaly, 2026, Tables 4, 7 and 10
3. [Power Transformer 40 MVA, FPT1847100 (EPDITALY0935)](https://epditaly.it/en/wp-content/uploads/2016/12/Matelec_EPD_FPT1847100-110118-40MVA.pdf) Matelec SAL, registered with EPDItaly, 2025, Tables 3, 4, 5 and 23
4. [Environmental Product Declaration Power Transformers 40/50 MVA (ONAN/ONAF), registration S-P-00053](https://library.e.abb.com/public/35e0a9e323ba7a88c1256de9003fdcd0/PT%2040-50%20MVA.pdf) ABB T&D S.p.A., 2003
5. [Environmental Product Declaration: String Power Inverters SG350HX, SG285HX, SG320HX, SG333HX (EPDITALY0458)](https://www.epditaly.it/wp-content/uploads/2016/12/EPD-of-Sungrow-power-inverter_Revision0610.pdf) Sungrow Power Supply Co., Ltd., registered with EPDItaly, 2023, Tables 4-1, 4-2, 5-1 and 7-1
6. [ABB general machinery drives, ACS350, 7.5 kW: Environmental product declaration](https://library.e.abb.com/public/943d18282cd8147ac1257403003c1f82/EPD-ACS350-EN.pdf) ABB, 2008
7. [Electric Grid Supply Chain Review: Large Power Transformers and High Voltage Direct Current Systems](https://www.energy.gov/sites/default/files/2022-02/Electric%20Grid%20Supply%20Chain%20Report%20-%20Final.pdf) US Department of Energy, 2022, Executive summary and sections 2.1.4 and 2.1.6
8. [Power transformers and distribution transformers will face supply deficits of 30% and 10% in 2025](https://www.woodmac.com/press-releases/power-transformers-and-distribution-transformers-will-face-supply-deficits-of-30-and-10-in-2025/) Wood Mackenzie, 2025
9. [Building the Future Transmission Grid: executive summary](https://www.iea.org/reports/building-the-future-transmission-grid/executive-summary) IEA, 2025
10. [Global PV inverter shipments grew by 10% in 2024 to 589 GWac](https://www.woodmac.com/press-releases/global-pv-inverter-shipments-grew-by-10-in-2024-to-589-gwac/) Wood Mackenzie, 2025
11. [India Adds 113,013 MVA Grid Transformation Capacity In FY26; Meets 90% Of CEA Target (syndicated press release)](https://www.outlookbusiness.com/spotlight/news-wire/india-adds-113013-mva-grid-transformation-capacity-in-fy26-meets-90-of-cea-target) Outlook Business, 2026
12. [Power Transformer Prices in India 2026: Costs Reach ₹23.37 Crore for 500 MVA Units as Lead Times Extend to 24 Months](https://greentechlead.com/?p=56421) GreentechLead, 2026
13. [Preparatory study for solar photovoltaic modules, inverters and systems, Draft Report Task 4: Technical analysis including end-of-life](https://susproc.jrc.ec.europa.eu/product-bureau/sites/default/files/contentype/product_group_documents/1581689975/DraftReport_Task4.pdf) European Commission Joint Research Centre, 2018

## Other sections

- [Summary](https://www.materialinsights.org/products/p_transformer_and_power_converter/index.md)
- [Working](https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-working/index.md)
- [Bill of materials](https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-bom/index.md)
- [Supply chain](https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-supply/index.md)
- [Footprint](https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-footprint/index.md)
- [Evolution](https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-evolution/index.md)
- [Interventions](https://www.materialinsights.org/products/p_transformer_and_power_converter/prod-interventions/index.md)