When a tanker dragged its anchor across Estlink 2 on Christmas Day 2024, 650 MW vanished for about six months.
Chart: Illustration: Underground, submarine and superconducting cables
Where it comes from
Chart: Map of where it comes from
A power cable swaps air for solid insulation around a thick copper or aluminium core. On land, 400 kV cables sit about 1.2 m deep, with joint bays every 500-1,000 m.
Three things to know
- Cable failures make up about 80% of offshore wind insurance claims, and fixing an export cable fault takes about 60 days.
- Superconducting cables lose no power in the conductor but need constant cooling to about minus 200 C; Munich plans a 15 km, 500 MW link.
- Old lead-sheathed cables hold about 12 kg of lead per metre, which makes deciding whether to remove them tricky.
The journey
- 1 SubstationConverter stations at each end for DC
- 2 Copper coreFat conductor, up to 2,500 mm²
- 3 InsulationXLPE plastic or oil-soaked paper
- 4 LayingTrench, tunnel or ploughed seabed
- 5 DeliveryCities, offshore wind and neighbouring countries