Compressed-air and CO2 storage: What to track

Real efficiency, Willow Rock's finance and India's first CO2 plant

Real efficiency, Willow Rock's finance and India's first CO2 plant What this tab covers The attributes worth tracking regularly, with the latest value, the direction of travel and why each matters.

Track whether adiabatic plants meet design efficiency in operation, and whether Willow Rock reaches financial close and construction.

CategoryAttributeLatestTrendWhy it matters
Techno-economicLCOS trajectoryAbout USD 100/MWh at 1,000 MW, 10 h (DOE/PNNL 2022)6↗ improving Large Chinese builds and longer durations should lower cost per kWh.
TechnicalMeasured round-trip efficiency (in place of state of health)Design 72.1% (Feicheng), 64-70% (Yingcheng) (developer figures); 60-65% (Hydrostor estimate); over 75% (Energy Dome claim)181113↗ improving Operating data will show whether the efficiency gap to pumped hydro is closing.
Supply chainCritical mineral cost and geopolitical concentrationNo critical minerals; build led by China19→ stable Risk lies in turbomachinery supply and geology, not minerals.
MarketAncillary service and capacity market accessLong-term contracts, such as 200 MW over 25 years at Willow Rock3↗ improving Lumpy projects need long contracted revenue to be financed.
ESG complianceSafety and environmental compliancePressure, mining and permitting rules; Willow Rock received its final California Energy Commission licence (Dec 2025)20→ stable Permitting is now cleared at Willow Rock; elsewhere it remains the main schedule risk.
ClimateLifecycle carbon payback periodNo verified figure found4→ stable Gas burned in diabatic plants matters; adiabatic plants should be much lower carbon.
PolicyUS federal support for Willow RockConditional DOE loan guarantee up to USD 1.76 billion (January 2025); no financial close found in reporting reviewed; company says shovel-ready in 20263420↕ volatile Conditional commitment issued just before a change of administration; watch final close.
DeploymentIndia and Asia uptake of CO2 and air storageNTPC Kudgi 160 MWh Energy Dome plant contracted (2025)9↗ improving First Indian utility deployment of a non-lithium, non-hydro long-duration store.
DeploymentHydrostor Silver City progressNSW development agreement approved Feb 2025 (company); AEMO and Transgrid connection approval Sept 20261112↗ improving First Hydrostor plant at scale; tests the water-column design and its cost.
PolicyGB cap-and-floor supportTeesCAES (50 MW, 30 h) on Ofgem's June 2026 minded-to list, the only CAES project among 1621↗ improving A regulated revenue floor is the route to finance for lumpy long-duration plants in Britain.

Sources

  1. 'World's largest' compressed air energy storage project connects to the grid in China Energy-Storage.news, 2024
  2. Hydrostor gets $1.76B DOE conditional loan guarantee for compressed air energy storage Utility Dive, 2025
  3. US DOE offers US$1.76 billion loan to Hydrostor for A-CAES California project Energy-Storage.news, 2025
  4. 2022 Grid Energy Storage Technology Cost and Performance Assessment US Department of Energy / Pacific Northwest National Laboratory, 2022
  5. Google backs Italian long duration CO2 energy storage technology RenewEconomy, 2025
  6. NTPC joins forces with Energy Dome for CO2 Battery deployment Energy Dome via Business Wire, 2025
  7. Hydrostor secures grid connection for first Australian CAES project ESS News, 2026
  8. Silver City Energy Storage Centre Hydrostor, 2026
  9. World's largest compressed air energy storage power station launched China Daily (Shandong), 2024
  10. World's largest compressed air energy storage project breaks ground in China ESS News, 2024
  11. Hydrostor's Willow Rock Energy Storage Center obtains final approval for power plant licence Hydrostor via Business Wire, 2025
  12. Long Duration Electricity Storage cap and floor Window 1: minded-to decisions (consultation) Ofgem, 2026