Fusion reactors: Resources and labour
Superconducting magnets, beryllium armour and a few grams of fuel
What this tab covers The natural resources (land, water, materials, fuel or feedstock) and the labour needed to capture this energy, per unit, with the reason each is needed.A fusion plant is a large, metal-intensive machine: superconducting magnets, beryllium or tungsten armour, steel structure and a lithium blanket. Fuel mass is tiny.
Natural resources
| Resource | How much | Why it is needed |
|---|---|---|
| Superconducting wire and tape | ITER: 100,000 km of niobium-tin strand (over 400 tonnes). SPARC: about 10,000 km of high-temperature superconducting tape.1214 | Only superconductors carry the currents for confining fields (20 tesla in the SPARC test magnet) without resistive losses that would consume the plant's output. |
| Beryllium, copper alloy and stainless steel (first wall) | 440 panels of about 1 x 1.5 m with 6-10 mm of beryllium tiles, rated for 2 to 4.7 MW/m2 of heat13 | Light beryllium atoms knocked off the wall cool the plasma less; copper conducts the heat to the coolant. |
| Steel and structural metal | ITER machine about 23,000 tonnes; vacuum vessel with ports, blanket and divertor 8,000 tonnes412 | The vessel holds a vacuum, resists forces from magnets storing up to 41 GJ, and shields the magnets from neutrons. |
| Land | ITER site 180 hectares, main platform 42 hectares12 | Tokamak building, tritium and cryogenic plants, power supplies and assembly halls. |
| Fuel (deuterium, tritium bred from lithium) | Less than 4 grams in the ITER vessel at any moment16 | Energy per kilogram is enormous, so fuel is a minor resource; lithium is covered on the Fusion fuels tile. |
Labour
| Phase | How much | Skills | Why it is needed |
|---|---|---|---|
| Construction (research machines) | About 5,000 people at ITER, up from about 1,400 in 201412 | Precision heavy engineering, welding, cryogenics, vacuum and nuclear-grade quality control | Components weighing hundreds of tonnes must be aligned to millimetres. |
| Manufacturing and supply chain | About 4,600 direct staff at private fusion firms and an estimated 9,300 supply-chain jobs; over 18,000 projected to build pilot plants15 | Superconductors, lasers and optics, power electronics, remote handling | Most hardware is first-of-a-kind and made to order. |
| Operation (experiments) | Over 300 scientists and engineers in JET's final deuterium-tritium campaign6 | Plasma physics, diagnostics, control, tritium handling | Each pulse is an experiment needing analysis and machine protection. |
| Jobs per MW | No estimate exists, because no plant generates electricity15 | Not applicable | Workforce intensity can only be judged once commercial plants are built. |
Neutron damage means wall components must be replaced periodically, adding to material throughput over a plant's life.
Sources
- Baseline press conference summary, July 2024 ITER Organization, 2024
- JET's final tritium experiments yield new fusion energy record UK Government (DESNZ / UKAEA), 2024
- Facts and figures ITER Organization, 2025
- Blanket first wall ITER Organization, 2025
- This Fusion Reactor Is Held Together With Tape IEEE Spectrum, 2024
- The global fusion industry in 2025 Fusion Industry Association, 2025
- Safety and the environment ITER Organization, 2025