AC transmission: Unit economics

What a mile of high-voltage line really costs

What this tab covers What it costs to move a unit of energy this way: capital and operating costs, tariffs, utilisation and how it compares with the alternatives.

A new high-voltage AC line costs roughly USD 4 to 6 million per mile in the US. Spread over decades of use, the cost of moving a MWh is modest compared with generating it, but equipment prices are rising.

Key costs

MeasureValueNote
New 345 kV double-circuit line, TexasAbout 4.2 USD million per mile6ERCOT planning estimate, 2025; about USD 2.6 million per km (calculated)
New 765 kV single-circuit line, MISO cost guide5.2 to 6.3 USD million per mile15MISO 2024 Transmission Cost Estimation Guide, as cited by AEP to the Texas PUC; AEP's own recent 765 kV line cost about 3.75
Texas 765 kV plan versus 345 kV planAbout 33.0 versus 30.8 USD billion6Whole-plan estimates including substations, January 2025; about 7% more for 765 kV (calculated)
MISO 765 kV Iowa line (EASL)About 1.23 USD billion8187 miles of 765 kV plus 22 miles of 345 kV and a new substation; about USD 5.9 million per mile all-in (calculated)
Cost to move 1 MWh 1,000 km, 765 kV single circuitAbout 21 to 26 USD/MWh515Calculated: line cost from the MISO guide only, 8% over 40 years, 2,435 MW at 60% utilisation; excludes substations, losses and operation
Cable and transformer pricesCables nearly doubled since 2019; transformers up about 75% real terms3IEA, 2025
Lead time, large power transformersUp to 4 years23Average lead times almost doubled since 2021

Where the money goes

ItemShare or amount
Line (AEP Greentown to Reynolds 765 kV, about 64 miles)About USD 240 million, about 69% (calculated)15
Substations (same project)About USD 107 million, about 31% (calculated)15

Utilisation matters as much as build cost: a line run at 60% of its rating spreads its fixed cost over twice as many MWh as one run at 30%. Losses add a running cost, which is why higher voltages often pay back on busy corridors.

AC lines are cheapest for short and medium distances; HVDC wins on long routes and under the sea. Spending must rise: the IEA says transmission investment needs to exceed USD 200 billion a year by the mid-2030s, up from USD 140 billion in 2023.

Sources

  1. Building the Future Transmission Grid: Executive summary IEA, 2025
  2. Rising component prices and supply chain pressures are hindering the development of transmission grid infrastructure IEA, 2025
  3. Discussion of EHV and HVDC (M. Tackett, MISO, presentation to ERCOT) MISO / ERCOT, 2023
  4. 2024 Regional Transmission Plan: 345 kV Plan and Texas 765 kV Strategic Transmission Expansion Plan ERCOT, 2025
  5. MISO selects Ameren, GridLiance and Dairyland consortium for EASL 765 kV project (reporting MISO's cost estimate) American Public Power Association, 2026
  6. AEP Companies' comments about extra high voltage transmission lines to the ERCOT region (Project 55249, citing MISO 2024 Transmission Cost Estimation Guide) Public Utility Commission of Texas, 2024