- Large transformers can take up to four years and HVDC cables over five, after prices rose 75% and nearly 100% since 20192.
- India has one CRGO plant of about 50,000 tonnes a year against electrical steel imports above 771,000 tonnes in 20234.
- India is over 90% import-dependent for power semiconductors and overall import dependence rose to 33% in 20251.
- China supplied nearly 30% of the roughly US$ 500 billion of global trade in the main categories in 2024, so trade barriers on either side reshape supply1.
- Copper, aluminium and rare-earth magnet prices pass directly into cable, motor and transformer costs.