Gravity storage: Evolution

Timeline

The milestones from first idea to today

YearMilestone
2013ARES completes a rail-car demonstration at Tehachapi, California [5]
2020Ground is broken in October for a 50 MW ARES rail plant at Pahrump, Nevada [6]
2021Gravitricity builds a test rig at Leith Port, Edinburgh [3]
2023Gravitricity starts a commercial-scale demonstration [3]
2023Energy Vault's 25 MW, 100 MWh block plant at Rudong, China, is connected to the grid in December [1]

as of 2026-11-12

Lineage

The technologies it came from and the ones that came from it

Can replace
  • PHS Pumped hydro storage Both store energy by raising mass; pumped hydro lifts water and reaches higher energy density, about 0.5 to 1.5 Wh/kg against 0.1 to 0.5 for solid weights [3].
Works with
  • WOn Onshore wind The Rudong plant charges from a nearby wind farm and discharges to the grid [1].
Builds on

as of 2026-11-12

Sources

  1. Energy Vault China gravity ESS project connected to grid; starts building three others Energy-Storage.news (no date or author shown; the text dates it to early March 2024)
  2. A Review of Gravity Energy Storage Energies 18(7), 1812 (R. Wang, L. Zhang, C. Shi and C. Zhao), MDPI, doi:10.3390/en18071812, 2025
  3. ARES Gravity Energy Storage Overview and Lessons Learned Sandia National Laboratories, slides supported by the DOE Office of Electricity (no date or presenter shown)
  4. Energy storage project breaks ground in Pahrump Pahrump Valley Times, 2020