Onshore wind: Resources and labour
Concrete, steel and people: what a wind farm really consumes
Per megawatt, an onshore wind farm is mostly concrete and steel, with smaller amounts of copper, aluminium, glass fibre and, in some designs, rare-earth magnets.
Natural resources
| Resource | How much | Why it is needed |
|---|---|---|
| Concrete | About 457 t per MW (calculated from 22,836 t for 50 MW); 8,000 t per TWh (US DOE)78 | Massive foundations stop a tall tower overturning under the sideways force of the wind on the rotor. |
| Steel and iron | About 117 t per MW (calculated from 5,860 t for 50 MW); 1,920 t per TWh (US DOE)78 | Tall, stiff towers reach faster, steadier wind; nacelle frames, shafts and generators are steel or cast iron. |
| Glass fibre and polymers | About 7.4 t of fibreglass and 13.6 t of polymers per MW (calculated)7 | Long blades must be light and stiff. |
| Copper and aluminium | About 1.7 t of copper and 3.4 t of aluminium per MW (calculated)7 | Generator windings and collection cables carry large currents with low losses. |
| Critical minerals in total | About 10 t per MW (IEA, including copper, zinc and rare earths)8 | Direct-drive turbines use neodymium-iron-boron magnets instead of a gearbox. |
| Land | Median 130 ha per TWh per year directly; 12,000 ha including spacing10 | Turbines stand several rotor diameters apart for undisturbed wind; land between can still be farmed. |
Labour
| Phase | How much | Skills | Why it is needed |
|---|---|---|---|
| Manufacturing and procurement | About 380 person-days per MW (calculated from 18,967 per 50 MW)7 | Factory workers, welders, composite technicians | Towers, blades and nacelles are made in specialised factories. |
| Construction (installation and grid connection) | About 690 person-days per MW (calculated from 34,480 per 50 MW)7 | Civil workers, crane operators, electricians | Roads, foundations, cabling and heavy lifts are done on site. |
| Operation and maintenance | About 53 person-days per MW per year (calculated from 2,665 per 50 MW); 43% of lifetime labour7 | Wind technicians working at height | Moving parts need regular inspection over 20 years or more. |
| Decommissioning | About 170 person-days per MW (calculated from 8,420 per 50 MW)7 | Crane crews, demolition and recycling workers | Turbines are dismantled and sites restored. |
| All phases, global total | About 1.9 million wind jobs worldwide in 2024 (onshore and offshore), 61% of them in China9 | As above | Reflects where turbines are made and installed. |
IRENA's breakdown for a 50 MW farm totals 144,420 person-days over 20 years; its stated phase shares do not match its own phase tables, so the per-MW figures above are indicative.
Sources
- Renewable Energy Benefits: Leveraging Local Capacity for Onshore Wind, Executive Summary (50 MW wind farm, Tables 2-9 and materials table) IRENA, 2017
- Mineral Requirements for Electricity Generation (citing IEA 2021 and US DOE Quadrennial Technology Review 2015) World Nuclear Association, 2024
- Renewable Energy and Jobs: Annual Review 2025 (Table 1, 2024 employment) IRENA and International Labour Organization, 2026
- Land-use intensity of electricity production and tomorrow's energy landscape (Lovering, Swain, Blomqvist and Hernandez, PLOS ONE 17(7): e0270155) PLOS ONE, 2022