Solar photovoltaics: Resources and labour
Land, steel, glass, silver and a lot of Asian factories
PV needs no fuel and almost no water; its demands are land, bulk materials for frames and glass, purified silicon and small amounts of silver or rarer metals. About 96% of modules and components come from Asia.
Natural resources
| Resource | How much | Why it is needed |
|---|---|---|
| Land | Median about 2,000 hectares per TWh a year for ground-mounted PV (about 20 m2 per MWh, calculated); close to zero for rooftops6 | Sunlight delivers a fixed amount of energy per square metre, and rows must be spaced so as not to shade each other. |
| Steel, concrete and aluminium | Steel 56-68 t, concrete 47-61 t, aluminium 7.5-19 t per MW (two estimates)78 | Steel piles and racking resist wind and snow; aluminium frames stiffen modules; concrete anchors inverters and substations. |
| Glass | 46-70 t per MW78 | Toughened low-iron glass protects the cells for decades while letting light through; it is the heaviest part of a module. |
| Silicon | About 2.0 g per watt in 2024 (2 t per MW, calculated), down from 16 g per watt in 2004; older estimates 4-7 t per MW178 | Silicon is the light absorber; it is refined to very high purity, an electricity-intensive step, because impurities trap freed electrons. |
| Copper, silver and thin-film metals | Copper 4.6-7 t per MW; silver about 20 kg per MW (2018); CIGS needs about 10-27 kg indium and 3-7 kg gallium per MW78 | Silver paste forms cell contacts; copper carries current; indium and gallium form the CIGS absorber and are by-products of other metals. |
| Water | Median about 1 gallon (4 litres) per MWh, range 0-59 | Only for panel washing; PV has no steam cycle needing cooling. |
Labour
| Phase | How much | Skills | Why it is needed |
|---|---|---|---|
| Whole life of a 50 MW plant | 229,055 person-days, about 4,600 per MW (calculated); 7.2 million people worked in solar PV worldwide in 2024, 58% in China810 | Technicians, electricians, engineers, lawyers and financiers | With no fuel, the work is in equipment. |
| Manufacturing and procurement | 22% of the total (50,225 person-days for 50 MW)8 | Factory workers and technicians (64%), industrial engineers (10%) | Making silicon, wafers, cells, modules and inverters. |
| Installation and grid connection | 17% (39,380 person-days for 50 MW)8 | About 90% construction workers and technical staff | Piling, mounting, cabling and the substation. |
| Operation and maintenance | About 56% of lifetime labour (13,560 person-days a year for 50 MW)8 | Construction workers and technicians for cleaning and repairs, safety experts, engineers and operators | Cleaning, vegetation control, repairs and monitoring over about 25 years. |
| Decommissioning | 2% (5,150 person-days for 50 MW)8 | Technical and construction workers (73%), truck drivers and crane operators | Removing modules and frames for recycling. |
Sources
- Photovoltaics Report (updated 14 July 2026) Fraunhofer Institute for Solar Energy Systems ISE, 2026
- What are the land-use intensities of different energy sources? (summary of Lovering et al., PLOS ONE 2022) The Breakthrough Institute, 2022
- Raw materials demand for wind and solar PV technologies in the transition towards a decarbonised energy system (Carrara et al., EUR 30095 EN), Table 4 European Commission Joint Research Centre, 2020
- Renewable Energy Benefits: Leveraging Local Capacity for Solar PV IRENA, 2017
- Operational water consumption and withdrawal factors for electricity generating technologies: a review of existing literature (Macknick et al., Environmental Research Letters 7, 045802), Table 1 IOP Publishing (copy hosted by OpenEI), 2012
- Renewable Energy and Jobs: Annual Review 2025 (p. 20) IRENA and ILO, 2026