Material Insights · Understanding the Material World

Rail traction: Levers

Held back most by

Economics

The machine is mature, and India's broad gauge was 99.2% electrified by November 2025 [13], so in India this limit has largely passed. Elsewhere the open question is where wires pay: overhead lines cost about GBP 1 million per single track km in Denmark and Germany and GBP 2.2 million on Britain's Great Western line [12], and India expected to spend about Rs 1.1 crore per route km on its last 18,808 route km (calculated) [21]. Where traffic is thin, cost decides, not physics.

The six layers

Mathematics, science, engineering, production, economics, and resources and rules: what each gives, the idea in plain words, the limit (hard or soft) and how close today is, what could unlock it, and the maths behind it

Six layers make a technology possible, from the mathematics underneath to the resources and rules it needs at world scale. A hard limit comes from mathematics or nature and can only be sidestepped; a soft limit moves with effort, scale, money or policy.

  1. 1 Mathematics Hard limit

    Mathematics is the language of its physics

    What it gives. Two equations set the job: how hard the train must be pushed at each speed, and the power that needs [10].

    The idea. A physical law makes a train move and mathematics only describes it, so the role is language. The push needed is the running resistance, a + bv + cv² (the Davis equation), plus the pull of any slope, and the power at the wheel is that force times speed [10]. Because the speed-squared term is multiplied by speed, power climbs much faster than speed.

    The limit. Power is force times speed, so for a fixed power the pulling force must fall as speed rises [10].

    What could unlock it. A bigger power budget is the way round it: a 12,000 HP (9 MW) Indian electric freight locomotive hauls about 6,000 tonne rakes at up to 120 km/h [15].

    Mot Electric motors and drives

    Show the maths F = a + b × v + c × v2, P = F × v
    F
    the force the wheels must push with, in kilonewtons
    a
    the part of the resistance that does not change with speed (rolling), in kilonewtons
    b
    how fast resistance grows in proportion to speed, in kilonewtons per metre a second
    c
    how fast resistance grows with speed squared (air), in kilonewtons per (metre a second) squared
    v
    the speed of the train, in metres a second
    P
    the power needed at the wheels, in kilowatts

    In plain words. A train must be pushed against rolling friction and against the air. The air part grows very fast with speed. Power is how hard you push times how fast you go. So going faster needs more push and more speed together, and the power needed rises quickly.

    Worked example. Assumption (an illustration, not a real train): a train on level track with a = 15 kN, b = 0.15 kN per m/s and c = 0.01 kN per (m/s)². At 20 m/s (72 km/h), F = 15 + 3 + 4 = 22 kN and P = 22 × 20 = 440 kW. At 30 m/s (108 km/h), F = 28.5 kN and P = 855 kW: 1.5 times the speed needs about 1.9 times the power (calculated) [10].

  2. 2 Science Hard limit

    What it gives. Friction between wheel and rail turns the motor's torque into a push on the train [11].

    The idea. The most a wheel can push is the adhesion coefficient times the weight on the driven wheels times gravity [11]. The coefficient can range from 0.05 to 0.4 as the rail surface changes, and it changes every few metres [11]. Past that limit the wheel slips and the push is lost.

    The limit. Adhesion: the push at the rail cannot exceed the adhesion coefficient times the adhesion weight times g, with the coefficient between 0.05 and 0.4 [11].

    What could unlock it. Wheel-slip controllers hold each wheel near its best grip [11], and adding weight on the driven wheels raises the limit, since the push in the equation rises in step with that weight [11].

    Mot Electric motors and drives

    Show the maths FT = μ × W × g
    FT
    the push at the wheel-rail contact, in newtons
    μ
    the adhesion coefficient, a pure number between about 0.05 and 0.4
    W
    the adhesion weight: the mass resting on the driven wheels, in kilograms
    g
    the pull of gravity, 9.81 metres a second squared

    In plain words. Rub your hand hard on a table and it grips. Wet it and it slips. A train wheel is the same. The grip is only a small fraction of the weight pressing down. So a locomotive can never pull harder than that grip allows, however strong its motor.

    Worked example. Assumption: a locomotive with 120 tonnes (120,000 kg) on its driven wheels. With μ = 0.3, FT = 0.3 × 120,000 × 9.81 = about 353 kN; on a slippery rail with μ = 0.05 it is about 59 kN (calculated) [11]. A 9 MW locomotive [15] could in principle push 450 kN at 20 m/s (calculated: 9,000 kW ÷ 20 m/s), so grip, not the motor, would be the limit at low speed.

  3. 3 Engineering Soft limit

    What it gives. A transformer, converter and motors turn the line's electricity into force at the wheel, and run in reverse to brake [12].

    The idea. In ABB's modern traction chain the transformer, the converter, and the motor with gearbox lose 7.5, 4.7 and 12.2 units for every 100 units that reach the wheels, so about 80% of the energy drawn from the wire reaches the wheels (calculated: 100 ÷ 124.4) [20]. Electric trains are generally three times more energy-efficient than diesel trains, and regenerative braking recovers typically 20% of a train's electricity consumption [12].

    The limit. Losses on the way from wire to wheel (about 80% delivered, not 100%) and the adhesion limit cap what a locomotive delivers [20][11].

    Energy drawn from the wire that reaches the wheels

    Today (2018): 80% · Limit: 100% · 80% of the way to the limit

    A modern product: ABB's traction chain loses 7.5 units in the transformer, 4.7 in the converter and 12.2 in the motor and gearbox for each 100 at the wheels, so 100 ÷ 124.4 = 80% (calculated) [20]; counting auxiliaries and parked time it is about 70% (calculated: 100 ÷ 143) [20]. The limit is 100%: no machine gives out more energy than it takes in.

    What could unlock it. Regenerative braking puts about a fifth of the energy back on the line [12]; the nodes on regenerative braking and railway wireless power cover the options.

    Rgn Regenerative braking and motion recoveryRW Railway electrification and wireless power

  4. 4 Production Soft limit

    What it gives. Indian Railways built 1,681 locomotives in FY 2024-25, about 1,576 of them electric (calculated from the model names) [16].

    The idea. That was 209 more than the 1,472 of the year before [16]. Alstom's Madhepura plant delivered its 500th fully India-made WAG-12B electric locomotive in March 2025, under a EUR 3.5 billion contract for 800, with more than 85% of the components sourced locally [15].

    The limit. Factory throughput and local supply of components set how fast the fleet can be renewed; 500 of 800 locomotives were delivered by March 2025 [15].

    What could unlock it. A steady order book lets factories scale: 300 of the 800 locomotives were still to come in March 2025 (calculated) [15].

  5. 5 Economics Soft limit Binds most today

    What it gives. Electric traction costs more to build but less to run: the Government of India calls it "about 70% more economical than diesel traction", without saying on what basis [13], and the Railways Minister told the Lok Sabha it saved Rs 6,000 crore by shifting from diesel to electric energy, for a period the report does not state [18].

    The idea. The cost is the wires. Typical costs are circa GBP 1 million per single track kilometre in Denmark and Germany, against GBP 2.2 million for Britain's Great Western electrification [12]; in 2021 India estimated Rs 21,000 crore for its remaining 18,808 route km of broad gauge, about Rs 1.12 crore per route km (calculated) [21]. The Indian railway financier IRFC said its cost of borrowing was about 7% at the end of December 2025 and that it tries to keep it below 8% [17].

    The limit. The cost of the fixed wires and of money: each route must earn it back from its traffic [12][17].

    What could unlock it. The source says cost-effective electrification is best delivered as part of a rolling programme, which is how Denmark and Germany reached about GBP 1 million per single track km [12].

    Show the maths CRF = r ÷ (1 - (1 + r)-n), annual capital charge = capex × CRF
    CRF
    the capital recovery factor: the share of the up-front cost paid back each year
    r
    the yearly cost of money, as a fraction
    n
    the number of years over which the cost is paid back
    capex
    the up-front cost of the wires, in rupees per route km

    In plain words. You borrow to put up the wires and pay it back over many years with interest. Each year you owe a fixed slice of the cost. The higher the interest, the bigger the slice. Electric trains win only if the fuel they save each year is bigger than that slice.

    Worked example. Assumptions: capex Rs 1.12 crore per route km, India's 2021 estimate for its last 18,808 route km (calculated) [21]; r = 7%, IRFC's rupee cost of borrowing [17]; n = 40 years, assumed. The CRF is 0.0750, so the yearly capital charge is about Rs 8.4 lakh per route km (calculated) [19]. A route km of double track has two tracks to wire, so this is not comparable with the cost per single track km [12].

  6. 6 Resources and rules Soft limit

    What it gives. Electrification is built line by line, and the lines must be cleared and fed with power [13].

    The idea. In India the work is nearly done: 99.2% of the 70,001 route km of broad gauge was electrified by November 2025, and 46,900 route km were added between 2014 and 2025 [13]. Elsewhere three-quarters of passenger rail activity is on electric trains and freight is less electrified [14]. In the UIC tables, 82% of China's lines (2024) and 62% of Germany's (2024) are electrified (calculated) [5].

    The limit. Network share electrified rises only as fast as lines are wired: India's century-long journey is only now nearing its end [13].

    What could unlock it. Mission 100% Electrification commits India to wire the whole broad gauge network, with no deadline given on the page [13]; the site's note on high-speed rail covers electric lines built for speed.

    HSR High-speed railRW Railway electrification and wireless power

as of 2026-11-23

Sources

  1. Railway Statistics Synopsis, 2025 edition International Union of Railways (UIC), 2025
  2. Mathematical Modeling for Holistic Convex Optimization of Hybrid Trains arXiv (Jibrin, Hillmansen, Roberts), 2021
  3. Summary of the Modern Wheel Slip Controller Principles Transactions on Electrical Engineering, CTU in Prague (Pichlik), 2019
  4. Why Rail Electrification? RailDecarb21 with the Railway Industry Association (Shirres, Keenor, Dolphin, Hooper), 2021
  5. Mission 100% Electrification: Powering the Future of Indian Railways Press Information Bureau, Government of India, 2026
  6. The Future of Rail IEA, 2019
  7. Alstom delivers the 500th electric locomotive for Indian Railways from its Madhepura site Alstom, 2025
  8. Indian Railways achieves production of 1,681 locomotives during FY 2024-25 Indian Infrastructure, 2025
  9. IRFC's Plans: Making all efforts to keep cost of borrowing below 8%, says IRFC CMD Dubey Informist Media, 2026
  10. Switching to electric power has saved Railways Rs 6,000 crore: Vaishnaw in Lok Sabha ThePrint (PTI), 2026
  11. Simple levelized cost of energy (LCOE) calculator documentation National Laboratory of the Rockies (formerly NREL), US Department of Energy, 2026
  12. Traction systems for high-power applications (brochure, Rev B) (company data) ABB, 2018
  13. Electrification of Railway Network (Rajya Sabha reply) Press Information Bureau, Ministry of Railways, Government of India, 2021