Material Insights · Understanding the Material World

Nuclear fission reactors: Resources and labour

Lots of concrete, little fuel and decades of skilled labour

What this tab covers The natural resources (land, water, materials, fuel or feedstock) and the labour needed to capture this energy, per unit, with the reason each is needed.

Nuclear power needs very little fuel and land per unit of energy, but a large concrete and steel structure, cooling water, enrichment services and a highly skilled workforce over a 60-plus-year life cycle.

Natural resources

ResourceHow muchWhy it is needed
Uranium68,920 tonnes U required in 2025 for 2,701.6 TWh, about 25 tonnes per TWh (calculated)4Only the small U-235 fraction is mainly used, so many tonnes of natural uranium are needed per tonne of fuel
Enrichment workAbout 140,000 SWU per year for a 1,000 MWe reactor; at 50 kWh/SWU that is about 7 GWh, roughly 0.1% of output (calculated)7Natural uranium (0.7% U-235) must be enriched to 3-5% to sustain a chain reaction in light water
Concrete, steel and other infrastructure materials0.6-1.4 tonnes per GWh generated14Thick concrete containment and shielding and a steel pressure vessel contain pressure and radiation
LandAbout 50 times less land per unit of electricity than coal15Fuel is extremely energy dense, so mining and plant areas are small
Cooling waterMedian 672 US gallons per MWh consumed (cooling towers); once-through cooling withdraws 44,350 but consumes 26916Two-thirds of reactor heat must be rejected, usually by evaporating water

Labour

PhaseHow muchSkillsWhy it is needed
ConstructionAbout 1,200 staff over a ten-year build; 12,000 labour-years per 1,000 MWe13Civil and nuclear engineers, welders, pipefitters, electricians, quality inspectorsNuclear-grade construction requires certified work and extensive inspection
OperationAbout 600 staff per year for 50 years; 30,000 labour-years per 1,000 MWe13Licensed reactor operators, radiation protection, maintenanceSafety rules require round-the-clock licensed crews
DecommissioningAbout 500 staff per year for ten years; around 5,000 labour-years13Decontamination, remote cutting, waste packagingRadioactive components must be dismantled safely
Waste managementAbout 80 staff over roughly 40 years; around 3,000 labour-years13Waste and storage specialistsSpent fuel must be cooled, monitored and eventually disposed of

Direct jobs total about 50,000 labour-years per 1,000 MWe, rising to about 200,000 job-years including supply-chain and induced jobs.

Sources

  1. World Nuclear Power Reactors and Uranium Requirements (updated 16 October 2026) World Nuclear Association, 2026
  2. Uranium Enrichment World Nuclear Association, 2025
  3. Study quantifies job creation in the nuclear sector (reporting OECD NEA and IAEA, Measuring Employment Generated by the Nuclear Power Sector) World Nuclear News, 2018
  4. Updated Mining Footprints and Raw Material Needs for Clean Energy The Breakthrough Institute, 2024
  5. How does the land use of different electricity sources compare? Our World in Data, 2022
  6. Operational water consumption and withdrawal factors for electricity generating technologies (Macknick et al., Environmental Research Letters 7, 045802) IOP Publishing (via OpenEI), 2012