Money, labour and the price of a tonne: The cost of capital and new supply
All courses / Understanding Commodities / Module 9: Money, labour and the price of a tonne Part 2 of 4The cost of capital and new supply
A mine looks like a hole in the ground. Financially it is a very large loan taken years before the first tonne is sold. The interest rate on that loan decides which deposits are worth opening, where, and at what price the metal must trade to make it worthwhile. This part works through the arithmetic with a copper mine and a home-loan style calculation.
2.1 A mine is mostly money paid upfront
Think of a home loan. The flat costs ₹60 lakh on the day you sign, and then you pay an EMI every month for twenty years. A mine has the same shape. Most of the spending comes first: drilling, shafts or pits, a concentrator, power lines, roads and water. Running costs, such as diesel, explosives and wages, come later and are spread across the tonnes sold. "Supply, demand and the cost curve" explains why the long-run price must cover this upfront cost, and why a mine takes many years to build. Here the question is how large the upfront cost is and what it costs to carry.
S&P Global looked at 26 copper projects scheduled to start by 2030. Dividing each project's development spending by the paid copper it will produce in an average year, the average came to $22,359 for each tonne of annual capacity. Projects ranged widely: about $10,566 to $37,553 in Latin America, while Kamoa-Kakula, an operating mine in the Democratic Republic of the Congo, came to $10,177. In the United States and Canada the average was $28,910.
Turn that into a project. A mine built for 200,000 tonnes of copper a year at the pipeline average needs $22,359 x 200,000 = about $4.5 billion (calculated). At the May 2026 rate of 95.56 that is roughly ₹42,700 crore. That sum is spent before a rupee of copper is sold, and it has to be raised from lenders and shareholders who will want a return for waiting.
The same logic holds across metals but not equally. A large open-cast iron ore pit usually needs far less capital per tonne of metal than a deep copper mine with a concentrator. Crushed stone, sand and gravel need almost none, since a quarry with a crusher and a few loaders can be set up cheaply, which is why they are produced close to every city. Capital matters most for deep, remote, low-grade or technically difficult deposits, and least for shallow, simple, local ones.
Two cautions apply. These are planning figures. Actual spending often overruns, and the S&P capital intensity is a ratio of development spending to annual output, not a price. And planning figures of this kind usually leave out interest paid during construction, so the real cost of carrying the loan is a little higher still.
2.2 The capital charge on a tonne
To compare a mine at two interest rates, spread the upfront sum over the years of output, the way a bank turns a loan into an EMI. The yearly payment for each unit borrowed is the capital recovery factor: rate divided by one minus (1 + rate) to the power minus years. For 25 years of life at 8%, the factor is 0.08 / (1 - 1.08^-25) = 0.0937. At 12% it is 0.1275. At 4% it is 0.0640 (all calculated).
Multiply by the capital per tonne of annual capacity. At $22,359, the yearly capital charge is about $1,431 a tonne at 4%, $2,095 at 8% and $2,851 at 12% (calculated). The same deposit, with the same shafts and the same crushers, costs about twice as much to carry at 12% as at 4%. Nothing about the rock has changed. Only the price of waiting has.
A price of copper that covers cash costs and a 4% capital charge may leave a 12% project short. That is why the long-run cost curve in "Supply, demand and the cost curve" is not fixed. It moves with interest rates. When rates rise across the world, the incentive price for new mines rises with them, and projects that looked sound at low rates drop out of the queue.
For a founder, this means a high-capital business has a long-term sensitivity to the rate that a low-capital one does not. A business that spends ₹1 crore on a quarry and recovers it in two years barely notices a rate change. A business that spends ₹4,000 crore and recovers it over twenty-five years feels every point. For an investor, it means asking not only for a project's cost but how much of it is capital and at what rate it was assumed. For a policy maker, it means that a state guarantee, a development-bank loan or a stable offtake contract works by lowering the rate, and a lower rate lowers the tonne's price.
| Cost of capital | Capital recovery factor | Yearly capital charge per tonne | Against the 4% case |
|---|---|---|---|
| 4% | 0.0640 | $1,431 | Base |
| 8% | 0.0937 | $2,095 | +46% |
| 12% | 0.1275 | $2,851 | +99% |
2.3 Why the same deposit is cheaper to open in a low-rate country
The cost of capital is not one number for the world. It depends on the lender's own funding cost, the risk of the country, the risk of the project and how long the money is tied up. Fewer reliable contracts, a slower court system, a weaker currency or a record of changing rules each raise it.
The IEA's work on clean energy shows the size of the gap. For utility-scale solar in 2019 it reported a cost of capital of 8.8 to 10.0% in India, against 2.6 to 5.0% in Europe and the United States. Financing was 20 to 50% of the levelised cost of the electricity. That is solar, not mining, and rates have moved since, but the lesson transfers: capital-heavy projects in higher-rate countries start with a handicap that cannot be removed by working harder. IEEFA reports that Indian solar and wind debt cost 8.5 to 9.75% in 2025. Equity costs more. Damodaran's January 2026 estimate of the total equity risk premium is 7.08% for India against 4.23% in Australia, a gap of 2.85 percentage points that comes from his country-risk estimate. Lenders and investors really do price the same dollar of risk differently depending on the country.
The IEA's mining outlook adds a related point: capital costs for projects in new, diversified supply regions are typically around 50% higher than for incumbent producers. Part of this is infrastructure that does not yet exist. Part is the price of money.
Read this with fairness. A low rate is not the only edge a country has. India has large deposits of iron ore, bauxite, coal and manganese, and where a mine's capital per tonne is low, the rate matters less than the grade of the ore and the distance to the market. Rates also fall when a country builds track record, which is why long-term contracts and transparent auctions are often proposed alongside public finance as ways to lower it.
- IEA, The cost of capital in clean energy transitions, 2021 (figures for 2019) · web
- IEEFA, Cost of capital for Indian renewable energy projects, 22 December 2025 · web
- Damodaran, Country default spreads and risk premiums, updated 5 January 2026 · web
- IEA, Global Critical Minerals Outlook 2025, executive summary · web
See it in the table
H₂O WaterCu CopperFe Iron oreMn ManganeseStn Crushed stoneEl ElectricityCheck your understanding
At the S&P average of $22,359 per tonne of yearly output, a 200,000 tonne a year copper mine needs roughly how much capital?
22,359 x 200,000 is about $4.47 billion.The same mine is financed at 12% instead of 4%, over 25 years. By roughly how much does the yearly capital charge per tonne rise?
The capital recovery factors are 0.1275 and 0.0640, a ratio of 1.99, so the capital charge roughly doubles.Which activity is least sensitive to the cost of capital?
A quarry needs little upfront money and recovers it quickly, so changes in the rate barely alter its cost per tonne.