Engineering economics: capital, people and the best design: Skills as a design limit
All courses / Understanding Engineering / Module 14: Engineering economics: capital, people and the best design Part 3 of 4Skills as a design limit
A design is finished only when someone can build it, fit it and mend it. Those people have skills of a certain kind and in a certain number, and that supply limits a design as firmly as the strength of steel. This part shows how installation changes performance, how big the training pipeline for solar installers must be, and how designers lower the skill a product needs.
3.1 A product performs in the field as well as the person who fits it allows
Think of the last time an air conditioner was fitted in a home. A technician drilled the wall, bent copper pipe, joined it, removed the air and set the refrigerant. The star rating on the label was measured in a laboratory with every step done well. The home gets the rating only if the fitter does the same.
A research report from the US National Institute of Standards and Technology, reported by the International Institute of Refrigeration in 2014, studied installation faults on ducted heat pumps and air conditioners of the kind used in US homes. Leaky ducts were the dominant fault. Too little refrigerant, and low airflow from undersized ducts, came next, and overcharging also mattered. In US field surveys, most of the air-conditioning equipment evaluated performed below its rated efficiency. The authors thought that poor installation could raise energy use by about 30 per cent, a figure they described as plausible rather than measured. Indian split units have no ducts, so the number is not an Indian measurement, but the principle carries over: field performance is rated performance multiplied by installation quality.
The sum is short. Assume a 1.5-tonne split air conditioner draws 0.9 kW on average for 1,500 hours a year, which is 1,350 kWh, or Rs 10,800 at Rs 8 a unit (calculated). A fault that adds 10 per cent costs Rs 1,080 a year and one that adds 30 per cent costs Rs 3,240. Over 10 years at a discount rate of 10 per cent the annuity factor is 6.145, so these faults cost Rs 6,600 and Rs 19,900 in today's money (calculated). A careful installer who charges a few thousand rupees more can pay for itself, if the buyer can tell who is careful.
Rooftop solar adds a safety side. The national qualification for a solar installer lists site survey, civil and mechanical work, electrical work including earthing and lightning arrestors, testing and commissioning, maintenance, and safe work at height. Each is a place where a shortcut hides until it fails. The module on Design, failure and safety shows how many failures begin in the field, not on the drawing.
For a founder, installation quality belongs inside the product warranty. For an investor, the installer network is part of the asset. For a policy maker, certification only helps if buyers can see it.
| Fault raises energy use by | Extra units a year | Extra cost a year | Cost over 10 years at 10% (annuity factor 6.145) |
|---|---|---|---|
| 10% | 135 kWh | Rs 1,080 | Rs 6,600 (calculated) |
| 30% (the NIST authors' plausible upper figure, for ducted US heat pumps) | 405 kWh | Rs 3,240 | Rs 19,900 (calculated) |
Base case: 0.9 kW x 1,500 hours = 1,350 kWh a year at Rs 8 a unit = Rs 10,800 (all assumed or calculated). Not a measurement of Indian installations.
Source: International Institute of Refrigeration, Energy efficiency of HVAC equipment suffers due to poor installation (2 December 2014), reporting a NIST research report on installation faults and heat pump performance, https://iifiir.org/en/news/energy-efficiency-of-hvac-equipment-suffers-due-to-poor-installation- International Institute of Refrigeration, Energy efficiency of HVAC equipment suffers due to poor installation (2 December 2014), reporting a NIST research report on installation faults and heat pump performance · web
- National Qualifications Register, Solar PV Installer (Suryamitra), Skill Council for Green Jobs · web
3.2 Skills come through a pipeline whose size and leaks can be counted
Who is allowed to call themselves a solar installer? The National Qualifications Register lists a Solar PV Installer (Suryamitra) at level 4 of the national framework, awarded by the Skill Council for Green Jobs. It takes 420 hours: 210 of theory, 150 of practical work and 60 on the job. Entry needs a pass in class 12 with science, or class 10 plus relevant years of experience or trade training. A Solar PV Installation Helper sits at level 2, takes 270 hours, and works under close supervision from age 16.
The wider pipeline is thin. The 2025 labour survey found that 4.2 per cent of people aged 15 to 59 reported formal vocational or technical training, and 5.0 per cent of those aged 15 to 29. Industrial training institutes are the main public route. In 2025 the skills ministry graded 14,580 of them for 2025-26. About 28 per cent scored above 8 out of 10, and 4.5 lakh seats that had stood empty for six years were taken off affiliation.
The demand is large. CEEW found about 1.1 lakh people working in India's renewable energy sector in 2021 and said around a million could be needed by 2030, mostly in small projects such as rooftop solar and mini-grids. The IEA counted 76 million energy workers worldwide in 2024 and found that more than half of 700 surveyed companies, unions and training bodies reported critical hiring bottlenecks, with applied technical roles such as electricians, pipefitters and line workers in short supply. India is not alone: in advanced economies there are 2.4 energy workers nearing retirement for every new entrant under 25.
The table turns CEEW's figures into training load. Training one person to the Suryamitra standard takes 420 hours, so 99,000 a year means 41.6 million trainee hours, about 3,960 batches of 25 (calculated). That is 2.5 times the pace of the Suryamitra drive of 2015 to 2017, which trained 78,000 people in two years.
One fairness point matters. The same CEEW source reports only 12,400, 5,200 and 6,400 new hires in the years 2018-19 to 2020-21. Training without jobs to go to does not create a workforce, and the pipeline has two ends: training capacity and demand for trained people.
| Step | Figure |
|---|---|
| Workforce, 2021 (CEEW) | about 110,000 |
| Potential, 2030 (CEEW) | about 1,000,000 |
| Extra people over 9 years | 890,000 (calculated) |
| Per year | about 99,000 (calculated) |
| Hours per person, Suryamitra standard | 420 |
| Trainee hours a year | 99,000 x 420 = 41.6 million (calculated) |
| Batches of 25 a year | about 3,960 (calculated) |
| Past pace: 78,000 trained in 2015 to 2017 | about 39,000 a year; the need is 2.5 times that (calculated) |
The 2030 figure is a potential from one study, and most of it would come from small projects.
Source: CEEW, India's renewable energy sector can employ one million people by 2030 (press release), https://www.ceew.in/press-releases/indias-renewable-energy-sector-employ-one-million-people-2030- National Qualifications Register, Solar PV Installer (Suryamitra), Skill Council for Green Jobs · web
- National Qualifications Register, Solar PV Installation Helper, Skill Council for Green Jobs · web
- MoSPI, Periodic Labour Force Survey Annual Report 2025, press note (27 March 2026) · web
- Business Standard, Third of ITIs graded above 8 in latest grading (20 July 2025) · web
- CEEW, India's renewable energy sector can employ one million people by 2030 (press release) · web
- IEA, Energy employment has surged but growing skills shortages threaten future momentum (2025) · web
3.3 Designers can lower the skill a product needs, but each way costs something
The flow shows the path from drawing to a working product. At each step a person with some skill takes a decision, and each decision can go wrong. A designer cannot train the nation, but can decide how many of those decisions the product leaves to people in the field.
One way is error-proofing. A plug that fits only one way cannot be wired backwards. A cost is a slightly dearer connector and less freedom for the fitter. A second is moving work into the factory. Parts that arrive assembled and tested bring factory quality control to a site where it is hard to supervise, at the price of a bulkier or more expensive delivery and less ability to fit odd sites. A third is built-in checking, such as indicator lights or a display that shows a fault. It costs a sensor and some software, and it gives a fitter and an owner something to act on. A fourth is margin: a design that still works tolerably when poorly fitted, as a pipe sized with room to spare does. It gives up some efficiency and material.
Repair needs the same thought. A ceiling fan, a pump or a tractor built from standard parts and common fasteners can be mended in a local workshop. A sealed unit that must be replaced as a whole is easy to install and hard to repair. That is a fair trade for a phone charger, whose price is lower than a repair visit, and a poor one for a borewell pump that serves a family's field.
Skill matters little where the product is finished in the factory and used as it arrives. A bulb, a charger or a sealed battery pack needs the skill in the plant, not in the home. Where the product is a system built on site, such as a rooftop plant, a water main or a heat pump with refrigerant lines, skill becomes part of the specification.
Skills can also be raised, and the facts give options. The IEA estimated that lifting the number of new qualified energy entrants by 40 per cent would cost an extra US$2.6 billion a year worldwide, under 0.1 per cent of global education spending, and named financial support for learners, apprenticeships and employer input to curricula. The next module, 'The money and people inside a product', looks at the jobs and skills behind everyday products.
factory skill and quality control; the most controllable step
2 Transport and storehandling damage and wrong parts are common faults
3 Installfitter's judgement on site: wiring, earthing, refrigerant, alignment
4 Commission and testthe last chance to catch a fault; needs the right tools and a checklist
5 Operate and repairowner and local mechanic; needs spares, standard parts and clear fault signs
Outputs Performance in the fieldrated performance x quality of every stepA step can be made less skilled by error-proofing, by moving it into the factory, or by building in a check.
Source: National Qualifications Register, Solar PV Installer (Suryamitra), Skill Council for Green Jobs, https://www.nqr.gov.in/qualification/file/New%20English%20QF_Solar%20PV%20Installer%20%28Suryamitra%29.pdfSee it in the table
H₂O WaterCu CopperCheck your understanding
Why does the NIST study's 30 per cent figure not transfer directly to Indian split air conditioners?
The principle that installation quality scales field performance carries over, but the size of the loss depends on the system and its dominant faults. The authors also called 30 per cent plausible, not measured.Roughly how many trainee hours a year does the training sketch require?
99,000 people a year x 420 hours each is about 41.6 million hours, or about 3,960 batches of 25 (calculated).A designer makes a product easier to fit by delivering it factory-assembled and tested. What is the usual price?
Moving work into the factory buys quality control but costs something in delivery, price or flexibility. Every way of lowering the skill a product needs has such a price.