Engineering economics: capital, people and the best design: Reading a Money card: the cost of capital by technology

All courses / Understanding Engineering / Module 14: Engineering economics: capital, people and the best design Part 4 of 4

Reading a Money card: the cost of capital by technology

Technology pages for which India has a published figure carry a Money card. It gives the cost of capital in India as a range with its year, the share of lifetime cost that is capital where a source gives one, and the reasons the rate is high or low. This part shows how to read one: which kind of rate it is, what a point of rate does to a yearly charge, and what the reasons point to.

4.1 A Money card gives a rate, a year and a basis, and the basis decides what the rate means

Rates on the cards are of three kinds, and they are not interchangeable. The cost of debt is the interest on loans, as in the What if rates of Part 1. The return on equity is what the owners of the project expect to earn on their own money, and for a regulated power station the regulator sets an allowed figure. The weighted average cost of capital, WACC, blends the two by the share of each, usually after tax. Equity is dearer than debt, so a card showing 15.5 per cent as an allowed return on equity does not mean the plant borrows at 15.5 per cent.

A short sum shows the gap. The regulator assumes that a new plant is funded 70 per cent by debt and 30 per cent by equity. If debt costs 8.5 per cent and equity earns 15.5 per cent, the blend is 0.7 x 8.5 + 0.3 x 15.5 = 10.6 per cent (calculated, before the effect of tax). A reader who compared 8.5 per cent for wind with 15.5 per cent for coal would think coal capital twice as dear. The blend is 25 per cent higher, not 82 per cent.

The same care applies to the What if rates. The project rate there, 9.125 per cent, is the middle of the debt band for Indian wind and solar. The solar card shows a WACC of 8.8 to 10.3 per cent, which is higher because the WACC carries equity too. The low end is the IEA's 2019 figure and the high end the 2024 figure, so the range spans five years, not two lenders.

Four checks before using a card: read the basis, read the year, notice whether the range comes from one source, and look at who set the number, the market or a regulator. Several cards give one figure from one station, one state or one order. The table lists the cards for which figures have been checked.

Data Cards with checked figures: the rate, what it is, and its year
TechnologyRate shownWhat kind of rateYear
Solar photovoltaics8.8 to 10.3%after-tax WACC2024 (low end is the IEA's 2019 figure)
Onshore wind8.5 to 9.75%cost of debt2025
Gas turbines and combined cycle7.71%cost of debt, one state-owned station's loans2026
Steam turbines and thermal power plants15.5%allowed return on equity2024
Hydropower dams17%allowed return on equity2024
Pumped hydro storage17%allowed return on equity2024
Nuclear fission reactors7.14 to 7.7%cost of debt, state operator's bonds2024 (7.7% in 2023)
HVDC links15%allowed return on equity2024
Run-of-river and small hydro9.38%regulator's WACC benchmark2026
Waste-to-energy9.08%regulator's WACC benchmark2026
Distribution grids, mini-grids and interconnectors14 to 15.5%allowed return on equity, one state2025

Three kinds of rate sit in one column: compare debt with debt and equity with equity. The 70:30 blend example is a calculation, not a card figure.

Source: CERC, Terms and Conditions of Tariff Regulations, 2024 (notification of 15 March 2024), https://www.cercind.gov.in/regulations/notification-2024.pdf

4.2 A point of rate matters most where capital is most of the cost and the asset lasts longest

The share of lifetime cost that is capital tells how far a rate reaches. For solar, the card gives 56 per cent, with a range of 55 to 57 per cent, worked out from Uttarakhand's tariff order for 2025-26 by adding the present value of depreciation, interest and return on equity and dividing by all costs over 25 years. For a new coal plant, about 65 to 70 per cent of the levelised tariff is fixed charges that recover capital and pay the allowed return. For nuclear, interest during construction can reach 30 per cent of project cost in traditional builds, so time itself is a cost.

The worked estimate uses the card's capital cost, a life and a capacity factor, the share of the year a plant effectively runs at full output. For solar the benchmark is Rs 2.78 crore a megawatt, one state's figure for 2025-26; the same order assumes a capacity factor of 19 per cent over a 25-year tariff. For small hydro the 2026-27 regulator's normative cost is Rs 12 crore a megawatt in hill states, and the same order uses a 45 per cent capacity factor there and a 40-year life. For nuclear, ICRA's range of Rs 16 to 20 crore a megawatt in 2025 has a midpoint of Rs 18 crore; its 40-year life and 80 per cent capacity factor are assumptions. Apply the capital recovery factor at 8.5 per cent and at 10.3 per cent, then divide the yearly charge by the units generated.

Two results follow. First, per unit of electricity the three are close, Rs 1.6 to 2.7 at 8.5 per cent, though capital per megawatt differs by more than a factor of six. A cheap megawatt that produces little is not cheaper per unit. Second, the same rise in rate, from 8.5 to 10.3 per cent, adds 15 per cent to the yearly charge for solar and 19 per cent for small hydro and nuclear, which both last 40 years. The longer the life, the more a rate counts.

Nuclear shows the effect of who borrows. At 7.14 per cent, the state operator's 2024 bond rate, the factor over 40 years is 0.0762 and the yearly charge Rs 137 lakh per megawatt. At the What if project rate of 9.125 per cent it is 0.0941 and Rs 169 lakh, 23 per cent more (calculated). This leaves out interest during construction, fuel and running costs, and it says nothing of when the power arrives, a point 'Cost, trade-offs and resources' made for levelised cost.

Data Worked estimate 7: the capital charge per kilowatt-hour at two rates
TechnologyCapital costLife and capacity factorCharge at 8.5%Charge at 10.3%Rise
Solar photovoltaicsRs 2.78 crore per MW (2025, one state)25 years, 19% (state regulator's norm)Rs 27.2 lakh per MW a year, Rs 1.63 a unitRs 31.3 lakh, Rs 1.88 a unit15%
Run-of-river and small hydroRs 12 crore per MW (2026, hill states)40 years, 45% (CERC norm, hill states)Rs 106.1 lakh, Rs 2.69 a unitRs 126.1 lakh, Rs 3.20 a unit19%
Nuclear fission reactorsRs 18 crore per MW (2025, midpoint of Rs 16 to 20 crore)40 years, 80% (both assumed)Rs 159.1 lakh, Rs 2.27 a unitRs 189.1 lakh, Rs 2.70 a unit19%

All charges are calculated: capital cost x capital recovery factor, divided by the units made at the stated capacity factor. Solar's 19% is Uttarakhand's normative figure (August 2025) and small hydro's 45% and 40 years are CERC's (August 2026); nuclear's life and capacity factor are assumptions. They leave out running costs, fuel, build time and tax, so they are not tariffs.

Source: Uttarakhand Electricity Regulatory Commission, Petition No. 51 of 2025, benchmark capital cost and generic tariff for solar PV, FY 2025-26 (20 August 2025), https://cdnbbsr.s3waas.gov.in/s3cf05968255451bdefe3c5bc64d550517/uploads/2025/08/20250820923945158.pdf, Table 1 and Annexure I

4.3 The reasons on a card show whether the rate is set by contracts, by regulators or by time

The tree groups the reasons that the checked cards give. The most common is the buyer. The main buyers of wind and solar power are state distribution companies, whose accumulated debt is Rs 6.84 trillion. The IEEFA review found that counterparty risk, whether the buyer pays on time, dominates the financing concerns in every study it covers. Over 50 GW of capacity auctioned has stalled because power purchase agreements were signed late. A lender cannot lend cheaply against a contract that is unsigned or a buyer who pays late.

The second is who sets the return. For thermal, hydro, pumped storage and transmission the regulator fixes a return on equity: 15.5 per cent for new thermal stations, 17 per cent for new storage-type hydro and pumped storage, 15 per cent for transmission. The buyer pays that return in the tariff, so it is a policy choice as much as a market price. State-owned borrowers, such as the nuclear operator with a AAA rating, borrow below private developers.

The third is time. A technology that takes years to build, such as a dam or a reactor, carries interest before it earns anything. The fourth is whether the market pays for the service. Financiers cited by Power Line in 2025 said that the biggest barrier to financing large storage is that no market yet pays for storage as a service, and that projects without firm contracts find money hard to raise.

These reasons point to where rates could move, which is not advice. The options follow from them and are for others to weigh: buyers paying their dues on time, agreements signed before auctions are awarded, and markets that pay for storage services. For a founder, a contract with a creditworthy buyer may cut the cost of capital by more than a better design does. For an investor, the card says where the risk is and who bears it. Part 1 showed that a rate shifts the best design; this part shows that the rate is itself shaped by contracts and rules. A technology without a card has a cost of capital too. The card is absent because no published Indian figure has been found, not because capital there is free.

Value chain Why a technology's cost of capital is high or low in India
  • Cost of capital on a Money card
    • Who pays the developer
      • State distribution companies owe lenders Rs 6.84 trillion, so payment risk is priced in
      • Late power purchase agreements: over 50 GW of auctioned capacity stalled
    • Who sets the return
      • Regulator-set return on equity: 15.5% thermal, 17% hydro and pumped storage, 15% transmission
      • State-owned, AAA-rated borrowers pay less than private developers
    • How long the asset takes to build
      • Interest during construction can be up to 30% of project cost in a traditional nuclear build
    • Whether the market pays for the service
      • No market yet pays for storage as a service, and projects without firm contracts struggle for finance
Source: IEEFA, Cost of capital for Indian renewable energy projects: review of methodologies, risk drivers and policy options (22 December 2025), https://ieefa.org/resources/cost-capital-indian-renewable-energy-projects-review-methodologies-risk-drivers-and

See it in the table

El Electricity

Check your understanding

Why is it misleading to compare a card showing 8.5 per cent for wind with one showing 15.5 per cent for coal?

Equity costs more than debt. A plant funded 70:30 at 8.5 per cent debt and 15.5 per cent equity blends to about 10.6 per cent, not 15.5.

In the worked estimate, why does the same 1.8-point rise in rate add more to nuclear's yearly capital charge than to solar's?

A 40-year asset gains 19 per cent and a 25-year asset 15 per cent from the same rise (calculated). The longer the balance stays outstanding, the more the rate counts.

Which reason on a card is mainly about contracts, not about the technology itself?

Stalled agreements and slow-paying buyers raise the rate lenders ask whatever the technology is. Interest during construction is about build time, and the regulated return about the rule that sets it.