Organic Rankine, Kalina and sCO2 cycles: Overview
What it does
The job the technology does for people, in a short paragraph
These cycles make electricity from heat that is too cool for an ordinary steam turbine. An organic Rankine cycle (ORC) boils a fluid with a much lower boiling point than water [4]. The first solar ORC units were shown in 1961 [2]. Turboden has commissioned a 13 MW ORC plant on two cement kiln lines at Riyadh Cement [10], and one of its pages reports more than 460 ORC units implemented worldwide [9].
as of 2026-11-12
How it works
The working principle in plain words, step by step
A pump sends a liquid working fluid through a heat exchanger, where waste heat turns it to vapour. The vapour spins a turbine on a generator, is condensed and pumped round again. In an ORC the fluid, for example propane, isopentane, isobutane or silicone oil [4], boils at a much lower temperature than water, so the cycle can run on heat sources at temperatures sometimes as low as 200°F [4]. The Kalina cycle uses two fluids with different boiling points, ammonia and water [4]. A supercritical CO2 cycle uses carbon dioxide above its critical point of 31.1°C and 73.8 bar [7]; a US pilot targets a turbine inlet of 500°C [8]. A Rankine cycle typically reaches 30 to 50% of the Carnot efficiency [4].
as of 2026-11-12
Key figures
The handful of numbers that size it up, each with its unit, year and source
| Figure | Value | Unit | Year | Source |
|---|---|---|---|---|
| Rankine cycle efficiency as a share of the Carnot efficiency, top of the 30 to 50% range | 50 | % of Carnot | 2021 | [4] |
| Capital cost of an organic Rankine cycle plant, top of USD 1,900 to 4,500 per kW | 4500 | USD/kW | 2021 | [4] |
| Installed waste heat to power capacity at over 100 US sites | 938 | MW | 2019 | [4] |
| ORC units implemented worldwide, more than, as stated on a Turboden page | 460 | units | 2026 | [9] |
| Output of the Riyadh Cement ORC waste heat plant | 13 | MW | 2026 | [10] |
| Size of the US supercritical CO2 pilot plant (STEP Demo) | 10 | MW | 2024 | [8] |
as of 2026-11-12. Years are publication years where the source gives no data year: 2021 for the DOE fact sheet's cost and Carnot-share ranges [4], 2026 for the Turboden and Riyadh Cement pages [9][10], 2024 for the STEP Demo release [8]. The 938 MW is for 2019 [4]; the fact sheet says steam and organic Rankine systems make up nearly all such plants.
Where it is used
The main places and products the technology is found in
- Cement kilns, where a 13 MW ORC plant recovers heat from two kiln lines [10]
- Geothermal binary power plants, the first installed in 1967 on Kamchatka [3]
- Solar thermal power, where the first ORC units were shown in 1961 [2]
- Industrial waste heat, as in the first commercial Kalina plant at Kashima, Japan [5]
- Demonstration of supercritical CO2 power at 10 MW in the US [8]
as of 2026-11-12
Scale today
How much of it there is now: units in use, made each year and who uses it
- Installed
- 938 MW of waste heat to power at over 100 US sites [4]
- Users
- Cement, geothermal, solar and industrial heat owners
- Unit
- MW
- Year
- 2019
- Note
- The US figure is from the DOE installation database and covers all waste heat to power, nearly all of it steam or organic Rankine [4]. A Turboden page reports more than 460 ORC units implemented worldwide [9]. No world total was found.
as of 2026-11-12
Sources
- Solar thermal powered Organic Rankine Cycles (chapter 16) Organic Rankine Cycle (ORC) Power Systems, Elsevier (Orosz and Dickes), copy on ORBi, University of Liège, 2017
- History KCORC (Kalina Cycle and Organic Rankine Cycle knowledge centre)
- Waste Heat to Power, CHP Technology Fact Sheet Series (DOE/EE-2347) US Department of Energy, 2021
- Kalina cycle enjoying commercial success Power Engineering, 2002
- Supercritical CO2 Power Technology: Strengths but Challenges Energies 17(5), 1129 (Molière, Privat, Jaubert, Geiger), 2024
- STEP Demo pilot plant achieves full operational conditions for Phase 1 of testing Southwest Research Institute, 2024
- Enhancing energy security and sustainability in cement plants through Turboden ORC technology Turboden (press review), 2026
- Turboden commissions 13MW waste heat power plant at Riyadh Cement CemNet (International Cement Review), 2026