Material Insights · Understanding the Material World

Railway electrification and wireless power: Levers

Held back most by

Engineering

Wired electrification is nearly done: 99.2% of India's broad gauge was electrified by November 2025, leaving 574 route km [10]. The open frontier is wireless power, and its published standard is for parked light vehicles, with levels up to 11 kVA today and 22 kVA in future revisions [9], far below what a train draws, so engineering is what money would change most. That limit is far from rail use today.

The six layers

Mathematics, science, engineering, production, economics, and resources and rules: what each gives, the idea in plain words, the limit (hard or soft) and how close today is, what could unlock it, and the maths behind it

Six layers make a technology possible, from the mathematics underneath to the resources and rules it needs at world scale. A hard limit comes from mathematics or nature and can only be sidestepped; a soft limit moves with effort, scale, money or policy.

  1. 1 Mathematics Hard limit

    Mathematics is the language of its physics

    What it gives. The law R = ρL ÷ A shows how far a train can run from a substation before the wire's resistance eats the voltage [11].

    The idea. A physical law does the work and mathematics only describes it, so the role is language. The resistance of a contact wire grows with its length and falls with its cross-section [11], so the voltage lost along it is the current times that resistance.

    The limit. Voltage drop along the wire: with resistance in the wire, a low-voltage, high-current supply loses much of its voltage within a few kilometres [11].

    What could unlock it. A higher supply voltage means a lower current for the same power, so substations can be placed farther apart [11].

    Show the maths R = ρ × L ÷ A, ΔV = I × R
    R
    the resistance of the wire, in ohms
    ρ
    the resistivity of the metal, in ohm metres
    L
    the length of wire, in metres
    A
    the cross-section of the wire, in square metres
    ΔV
    the voltage lost along the wire, in volts
    I
    the current drawn by the train, in amps

    In plain words. A wire pushes back on the current, and the push-back takes some of the voltage away before it reaches the train. Send the same power at a high voltage and you need less current, so less is lost.

    Worked example. R = ρL ÷ A is the source's [11] and ΔV = I × R is the definition of resistance given on the same page [11]. Assume a copper wire of resistivity 1.7 × 10-8 Ω m and 150 mm² (1.5 × 10-4 m²), and a train drawing 7.5 MW (all assumed). Each km has R = 1.7 × 10-8 × 1,000 ÷ 1.5 × 10-4 = 0.113 Ω (calculated). At 25 kV the current is 7.5 MW ÷ 25 kV = 300 A (power factor ignored), so ΔV = 300 × 0.113 = 34 V in each km, or 0.14% of the supply (calculated). At 750 V the current would be 10,000 A and ΔV = 1,133 V in each km, more than the supply itself (calculated).

  2. 2 Science Hard limit

    What it gives. Induction lets power cross an air gap: a changing current in one coil makes a voltage in another, which is how a wireless charging pad works [12][9].

    The idea. The voltage in the second coil is the mutual inductance times the rate of change of the current in the first [12]. The mutual inductance is a geometric quantity [12], so it depends on how the two coils are placed.

    The limit. The voltage made in the car's coil depends on M, which is set by geometry, and so by the gap and alignment between the coils [12]; this is why the standard also deals with alignment [9].

    What could unlock it. Faster current changes, meaning a higher frequency, raise the voltage for the same M; closer, better-aligned coils raise M [12].

    HVAC AC transmission

    Show the maths ε2 = -M × dI1/dt
    ε2
    the voltage made in the car's coil, in volts
    M
    the mutual inductance: how strongly the two coils are linked, in henries
    I1
    the current in the ground coil, in amps
    t
    time, in seconds

    In plain words. The pad in the ground carries a current that goes up and down very fast. The changing current makes a changing magnetic field, and that makes a voltage in the coil under the car, with no wire joining them. The better the coils line up, the bigger the voltage.

    Worked example. The equation is the source's [12]. For a sine current of peak Ip at frequency f, the peak of dI/dt is 2πf × Ip, so the peak voltage is 2πf × M × Ip (calculated). Assume f = 85 kHz, M = 20 µH and Ip = 50 A (all assumed). The peak voltage is 2π × 85,000 × 20 × 10-6 × 50 = 534 V (calculated).

  3. 3 Engineering Soft limit Binds most today

    What it gives. The SAE J2954 standard for wireless charging of light vehicles, revised in August 2024, defines three charging levels up to 11 kVA, and in future revisions up to 22 kVA [9].

    The idea. The standard addresses stationary light-duty applications, meaning charging while the vehicle is not moving [9]; railway locomotives take their power from the overhead wire.

    The limit. Power level and alignment: the standard's top level is 11 kVA today [9], far below the 7.5 MW assumed for a train in the maths row.

    What could unlock it. Higher power levels in future revisions of the standard [9].

    EV Electric and hybrid vehicles

  4. 4 Production Soft limit

    What it gives. Electrifying a railway is a repeated building job: masts, wire, substations and the lines to feed them [10].

    The idea. India electrified 46,900 route km between 2014 and 2025, about 4,300 a year over the 11 years (calculated), and 69,427 route km in all by November 2025 [10].

    The limit. The pace now falls because little is left to build: 574 route km remain on broad gauge [10].

    What could unlock it. Finishing the last routes is a matter of the same building methods, with no new technology needed (no source gives a date).

  5. 5 Economics Soft limit

    What it gives. The Press Information Bureau says electric traction is about 70% more economical than diesel traction [10].

    The idea. The Railway Minister told the Lok Sabha in March 2026 that shifting from diesel to electric energy had saved Rs 6,000 crore [13]. The case for a wire is already made where traffic is dense.

    The limit. Cost of the wire against traffic: the masts and substations are paid for up front, so the case is strongest where traffic is dense [10][13].

    What could unlock it. Fuel savings pay back the wire; the share of grid power that is renewable decides how much carbon is saved [10][13].

  6. 6 Resources and rules Soft limit

    What it gives. Almost all of India's broad gauge is electrified, so rules and land no longer hold wired electrification back [10].

    The idea. The PIB says Indian Railways has electrified about 99.2% of its network by November 2025, and that the rest is 574 route km, or 0.8% of the broad gauge network [10]. For wireless charging, a published standard for light vehicles exists [9].

    The limit. What is left is 574 route km of residual sections in five states [10].

    What could unlock it. Higher-power wireless levels, which the SAE says may come in future revisions up to 22 kVA [9].

as of 2026-11-23

Sources

  1. J2954_202408: Wireless Power Transfer for Light-Duty Plug-in/Electric Vehicles and Alignment Methodology SAE International (SAE Mobilus), 2024
  2. Mission 100% Electrification: Powering the Future of Indian Railways (PIB Backgrounder, 6 January 2026) Press Information Bureau, Government of India, 2026
  3. University Physics Volume 2, section 9.3: Resistivity and Resistance OpenStax, Rice University, 2016
  4. 14.1 Mutual Inductance (University Physics Volume 2) OpenStax, 2026
  5. Switching to electric power has saved Railways Rs 6,000 crore: Vaishnaw in Lok Sabha ThePrint (PTI), 2026