Steel plant energy recovery: Evolution

Timeline

The milestones from first idea to today

YearMilestone
1922Sulzer applies for a Swiss patent on cooling glowing coke with a fan-driven gas stream and a heat exchange device (priority 6 September 1922) [3]
1965The first full-scale coke dry quenching plant is commissioned at the Cherepovets Iron and Steel Works in the USSR, according to IspatGuru [1]; a UN centre dates industrial use to the early 1960s [2]
1974The first top-pressure recovery turbine plant in Japan is delivered, in September [5]
1976Three Japanese dry quenching installations start work in 1976 and 1977, after Japan bought a licence from the USSR in 1975 [1]
1978About 50 dry quenching modules are in operation in the USSR [1]
2006China owns 43 coke dry quenching systems by the end of the year [2]
2024Steelmaking uses 20.95 GJ per tonne, down from about 50 GJ per tonne in the 1960s [6]

as of 2026-11-12

Lineage

The technologies it came from and the ones that came from it

Came before it Builds on
  • TX Pressure and flow recovery A top-pressure recovery turbine takes power from the pressure of blast furnace gas as it expands to atmospheric pressure [5].
Works with

as of 2026-11-12

Sources

  1. Dry cooling of coke (practitioner article, second-hand) IspatGuru (Satyendra Kumar Sarna)
  2. Coke dry quenching for iron and steel sector UNFCCC Climate Technology Centre and Network (CTCN)
  3. Coke cooling system (CH101570A) Google Patents (Sulzer AG)
  4. Top-Pressure Recovery Turbine Plant (TRT), technology sheet S-08 Kawasaki Heavy Industries, on the Energy Conservation Center Japan's JASE-World site, 2024
  5. Energy use in the steel industry (fact sheet) World Steel Association, 2025