Material Insights · Understanding the Material World

Titanium: Extraction

Dredging ancient beaches for heavy mineral sands

What this tab covers How it is mined, drilled or grown, and processed into a tradeable form: the main methods compared, their unit economics, by-products, and the companies that do this work globally and in India.

Most titanium comes from ilmenite and rutile in heavy-mineral sands, dredged or surface-mined from old beaches and dunes. Zircon, monazite and abrasive sands are coproducts, as at the US operations in Georgia and Florida. Some ilmenite comes from hard-rock titaniferous magnetite, smelted to a high-TiO2 slag in Canada, South Africa and Madagascar. Ilmenite makes up about 90% of titanium mineral consumption. Concentrates are upgraded and turned into pigment. A small share is chlorinated and reduced with magnesium to porous sponge metal.

Titanium starts as two minerals: lower-grade ilmenite, an iron-titanium oxide, and high-grade rutile (traded at a minimum 95% TiO2, USGS). Most come from heavy-mineral sands, which also yield zircon and monazite, so a sands mine sells a basket of products. Low-grade ilmenite is upgraded to slag or synthetic rutile because the cleaner chloride pigment process needs high-TiO2 feed. About 90% of feedstock ends up as pigment. A small share is chlorinated and reduced with magnesium to sponge metal, a costly batch process that only a few countries run.

Methods compared

MethodShare of supplyTypical scaleRecovery / efficiencyBy-productsUnit cost
Mineral sands dredging or dry mining with mineral separationmost of world ilmenite (9.4 Mt TiO2) and rutile (0.45 Mt TiO2) output in 2025; exact sands share not published (USGS)Kenmare Moma: 842 kt ilmenite, 50 kt zircon, 8.6 kt rutile in 2025; Iluka: 159 kt zircon, 79 kt rutile, 335 kt ilmeniten/a zircon, monazite (rare earths, thorium), garnet, sillimaniteIluka unit cash production cost A$1,054/t of zircon, rutile and synthetic rutile (2025); Kenmare guides $240-250/t of finished product for 2026
Hard-rock ilmenite smelted to titanium slagSouth Africa, Canada and Madagascar produce titaniferous magnetite mainly for slag (USGS); share not publishedUS slag imports came mainly from South Africa (65%), Norway (24%) and Canada (10%) in 2025n/a pig iron and steel feedUS import unit value of 80-95% slag $880/t in 2025, against $300/t for ilmenite (USGS)
Synthetic rutile (Becher-type reduction and leaching)n/a Iluka produced 209.9 kt of synthetic rutile in 2025; Sierra Leone (78%) and China (21%) supplied US synthetic rutile importsn/a iron oxide residuen/a
TiO2 pigment: chloride and sulfate processesabout 90% of titanium feedstock demand (Iluka 2017)LB Group (China) produced 1.28 Mt of pigment in 2025 from 1.51 Mt/yr capacity; China holds 6.0 Mt of world 9.9 Mt capacity (USGS)n/a iron chloride (chloride route), ferrous sulfate and spent acid (sulfate route)US pigment import unit value $3,200/t in 2025 (USGS)
Kroll process to titanium spongeabout 6% of feedstock demand (Iluka 2017); world sponge output 370 kt in 2025LB Group 71.3 kt sponge in 2025 (80 kt/yr capacity); India's KMML plant 500 t/yr capacity, 300 t output (USGS)n/a magnesium chloride (recycled)US sponge import unit value $12/kg in 2025 (USGS)

How each method works

Mineral sands dredging or dry mining with mineral separation

A floating dredge or earthmovers feed sand to a wet concentrator of spirals, producing heavy-mineral concentrate of a few percent of the ore. A dry plant then separates ilmenite (magnetic), rutile and zircon (non-magnetic, split by conductivity) and monazite. Tailings are returned and the land rehabilitated.

Low-cost, multi-product mines; product prices move differently, and coastal sites face long permitting.

Iluka quarterly review Dec 2025; Kenmare Q4 2025 production report; USGS MCS 2026 Hard-rock ilmenite smelted to titanium slag

Ilmenite or titaniferous magnetite from hard-rock or sands deposits is smelted with coal in electric furnaces. Iron separates as high-purity pig iron and the titanium reports to a slag of 80-95% TiO2 that feeds pigment plants.

Upgrades low-grade ore and earns iron credits; electricity-intensive.

USGS MCS 2026 Synthetic rutile (Becher-type reduction and leaching)

Ilmenite is reduced in a coal-fired kiln to metallic iron, which is then rusted out and leached away, leaving high-TiO2 grains for chloride pigment and metal plants.

Makes premium chloride feed from cheaper ilmenite; kilns are energy- and emissions-intensive.

Iluka Dec 2025 quarterly; USGS MCS 2026 TiO2 pigment: chloride and sulfate processes

In the chloride process, high-grade feed is chlorinated with coke to titanium tetrachloride, purified and burnt with oxygen to pigment. In the sulfate process, ilmenite or slag is dissolved in sulfuric acid, hydrolysed and calcined. Pigment is then milled and surface-coated.

Chloride gives purer pigment and less waste but needs high-grade feed; sulfate takes cheap ilmenite but makes more waste.

USGS MCS 2026; LB Group via The Metalnomist (July 2026); Iluka (2017) Kroll process to titanium sponge

Purified titanium tetrachloride is fed onto molten magnesium in a sealed steel reactor; magnesium chloride forms and is drained, leaving a cake of porous sponge. The magnesium chloride is electrolysed back to magnesium and chlorine.

Proven route for aerospace-grade metal; slow batch process with high energy and capital costs.

USGS MCS 2026; The Metalnomist (July 2026) Unit economics are indicative ranges from the sources named; costs vary widely by deposit, region and year.

Share produced as a by-product

About 5% of primary supply comes as a by-product (Nassar, Graedel & Harper 2015, approximate).

Who does it: global

CompanyCountryActivityVolumeYearSource
LB Group (Lomon Billions)ChinaTiO2 pigment, titanium sponge, titanium concentrate mining1.28 Mt TiO2 pigment (plus 71.3 kt sponge and 1.45 Mt titanium concentrate) 2025LB Group 2025 results via The Metalnomist (July 2026)
Iluka ResourcesAustraliamineral sands mining, synthetic rutile559 kt zircon, rutile and synthetic rutile (zircon 159.2, rutile 78.9, SR 209.9; plus ilmenite 335.2 kt) 2025Iluka quarterly review to 31 Dec 2025
Kenmare ResourcesIreland/MozambiqueMoma mineral sands mine842 kt ilmenite (plus 50 kt zircon, 8.6 kt rutile) 2025Kenmare Q4 2025 production report
Tronox Volumes not published in tonnes; Tronox was among the four largest titanium and zirconium producers in 2013. US/UKmineral sands (South Africa, Australia), slag and chloride pigmentnot published 2025Tilton and Guzman (2016)
Rio Tinto (Rio Tinto Fer et Titane, Richards Bay Minerals, QMM) 2025 volume not found; Rio Tinto was among the top four titanium producers in 2013. UK/Australiahard-rock ilmenite and sands, slag and upgraded slagnot published 2025Tilton and Guzman (2016)
Japanese sponge producers (Osaka Titanium, Toho Titanium) Company split not published; Japan supplied 73% of US sponge imports in 2025. Japantitanium sponge53 kt sponge (Japan total) 2025USGS MCS 2026

Who does it: India

CompanyCountryActivityVolumeYearSource
IREL (India) Ltd Production by mineral not published. Indiabeach-sand mining and separation (Chavara, Manavalakurichi, OSCOM)262,900 t/yr processed minerals capacity at Chavara (ilmenite, rutile, zircon, sillimanite) not datedIREL website, Chavara Mineral Division
Kerala Minerals and Metals (KMML) Also runs India's only titanium sponge plant (500 t/yr, built with the Department of Space); India's sponge output was 300 t in 2025 (USGS). Net profit Rs 107.67 crore in FY2025 (Wikipedia). Indiamineral separation, TiO2 pigment, titanium sponge40,000 t/yr TiO2 pigment capacity (declared 2005) 2005KMML organisational details (RTI disclosure)

India mined 240 kt TiO2 of ilmenite and 13 kt of rutile in 2025, has 15 Mt of ilmenite and 670 kt of rutile reserves (USGS), and makes small amounts of sponge (300 t) and pigment (91 kt capacity). It exported $66.9 million and imported $69.8 million of titanium ores in 2024 (Comtrade). Titanium is on India's 2023 critical list.