Distribution grids, mini-grids and interconnectors: Levers
Held back most by
Economics
The physics is settled and the equipment can be bought, but in FY 2024-25 India's distribution companies were not paid for 15.04% of the energy they put in, counting heat in the wires, theft and unpaid bills [12], against a national aim of 12 to 15% [17]. They posted their first all-India profit, Rs 27.01 billion, after a loss of Rs 270.22 billion the year before [12]. Grids that must grow fast, with the IEA calling for investment that emphasises modernising distribution [14], need utilities that can pay for them.
The six layers
Mathematics, science, engineering, production, economics, and resources and rules: what each gives, the idea in plain words, the limit (hard or soft) and how close today is, what could unlock it, and the maths behind it
Six layers make a technology possible, from the mathematics underneath to the resources and rules it needs at world scale. A hard limit comes from mathematics or nature and can only be sidestepped; a soft limit moves with effort, scale, money or policy.
- 1 Mathematics Hard limit
Mathematics is the language of its physics
What it gives. Circuit mathematics tells a planner how much heat a line makes at a given current before anything is built [10].
The idea. A physical law makes the network work and mathematics only describes it, so the role is language. The power lost in a line is the current squared times its resistance, so for the same power a higher voltage means a smaller current and far less loss [10]. In the source's example, 100 MW sent 200 km loses 827 MW at 11 kV but about 2.07 MW at 220 kV [10].
The limit. Loss grows with the square of the current, so a low-voltage line cannot carry bulk power far [10].
What could unlock it. Raising the voltage on long runs is the way round it: in the source's example 20 times the voltage cut the loss 400 times (calculated) [10].
PE Transformers and power electronics
Show the maths
Ploss = I2 × R- Ploss
- the power lost as heat in the line, in watts
- I
- the current in the line, in amps
- R
- the resistance of the line, in ohms
In plain words. A wire gets warm when current goes through it. Double the current and it makes four times the heat. For the same power, a higher voltage needs less current. That is why power travels far at high voltage and is stepped down only near the user.
Worked example. The source's own case: 100 MW over 200 km, with a line resistance of 10 ohms (0.05 ohm for each km) [10]. Taking the current as power divided by voltage, as the source does, 11 kV gives 9,091 A and a loss of about 826 MW (the page prints 827 MW); 220 kV gives 455 A and about 2.07 MW, so 20 times the voltage gives 400 times less loss (calculated) [10].
- 2 Science Hard limit
What it gives. Metals carry current but resist it, and the resistance turns electrical energy into heat [11].
The idea. The resistance of a wire is its resistivity times its length divided by its cross-sectional area [11]. Copper's resistivity is 1.68 × 10-8 ohm metres, and resistivity is a property of the material [11]. A longer or thinner conductor therefore wastes more, so every feeder trades copper cost against heat lost.
The limit. Resistivity is set by the material, so a given conductor at a given current always loses a fixed amount as heat [11][10].
What could unlock it. A wider conductor or a higher voltage lowers the heat for the same power [10][11]; the cables node covers the materials.
Cab Underground, submarine and superconducting cables
Show the maths
R = ρ × L ÷ A- R
- the resistance of the conductor, in ohms
- ρ
- the resistivity of the material, in ohm metres (copper: 1.68 × 10-8)
- L
- the length of the conductor, in metres
- A
- the cross-sectional area of the conductor, in square metres
In plain words. Think of a pipe. A long, thin pipe lets less water through than a short, wide one. A wire is the same for electricity. Make it longer and the resistance goes up. Make it thicker and it goes down.
Worked example. Assumption: 1 km of copper conductor of 50 mm² (5.0 × 10-5 m²) carrying 200 A. R = 1.68 × 10-8 × 1,000 ÷ (5.0 × 10-5) = 0.336 ohm, so the heat is 200² × 0.336 = about 13.4 kW for each kilometre (calculated) [11].
- 3 Engineering Soft limit
What it gives. Engineering turns the loss law into real feeders, choosing voltage and conductor so that the heat lost stays small for the power carried [10].
The idea. The voltage is chosen first: at 11 kV the source's line could not carry 100 MW over 200 km at all, because the loss exceeded the power sent [10]. The IEA says grid investment should be raised with emphasis on digitalising and modernising distribution grids [14].
The limit. A line or transformer can carry only the current its heating allows, because losses are proportional to the square of the current and show up as heat [10].
What could unlock it. Digitalised and modernised distribution grids are the IEA's stated route to more use of the wires already built [14].
PE Transformers and power electronicsCab Underground, submarine and superconducting cables
- 4 Production Soft limit
What it gives. Distribution needs transformers and cables in the millions, and transformers are the pinch point [15][16].
The idea. An IEA survey found that procurement takes two to three years for cables and up to four years for large power transformers, twice as long as in 2021 [15]. In real terms cable costs have nearly doubled since 2019 and power transformer prices are up about 75% [15]. India's power sector faced a 30% shortage of grain-oriented electrical steel: in 2023-24 it needed 400,000 tonnes, only 50,000 were made at home and 239,000 were imported [16].
The limit. Factory capacity and the supply of electrical steel, not the design, set how fast new transformers can be installed [15][16].
What could unlock it. More domestic output of electrical steel would cut import dependence; the source gives no date for India's gap to close [16].
- 5 Economics Soft limit Binds most today
What it gives. A distribution company earns only on the units it bills and collects: in FY 2024-25 India's aggregate technical and commercial loss fell to 15.04% from 15.97% [12].
The idea. AT&C loss counts heat in wires, theft and unpaid bills together, as the share of the energy put in that was never paid for [13]. The gap between average cost of supply and revenue narrowed from Re 0.32 to Re 0.07 a kWh in FY 2024-25 [12]. Off the grid, solar mini-grid power fell from 0.55 to 0.38 US dollars a kWh between 2018 and 2022 [4].
The limit. Losses and collection: every unit not paid for is revenue lost, and the sector's cost-revenue gap is now only Re 0.07 a unit [12].
AT&C loss: share of the energy put in that is never paid for, India
Today (2025): 15% · Floor: 12% · today is 1.3 times the floor
Typical: the all-India average for FY 2024-25 in the Ministry of Power's 14th rating report [12], against the low end of the government's aim of 12 to 15% for India as a whole [17]. The limit is a policy target, not a law of nature.
What could unlock it. The government's distribution scheme aims to bring the all-India loss down to 12 to 15% [17]; the fall of 0.93 percentage points in one year shows the lever works [12].
Show the maths
L = U ÷ E × 100- L
- the AT&C loss, in per cent
- U
- units unrealised: energy put into the network that was not paid for, in million kWh
- E
- net input energy: the energy put into the network, in million kWh
In plain words. Put 100 units of electricity into the network. Some turns to heat in the wires. Some is stolen. Some is billed but never paid. Count all the units that brought in no money. That share is the loss. The lower it is, the more money the company has to repair and grow the network.
Worked example. FY 2024-25: a loss of 15.04% means about 15 of every 100 units put in brought in no money and about 85 did (calculated: 100 - 15.04 = 84.96) [12][13]. The fall from 15.97% is 0.93 percentage points, or about 0.9 more paid units for every 100 put in (calculated) [12].
- 6 Resources and rules Soft limit
What it gives. Wires must be planned, permitted and built at world scale, and homes outside the grid need another route [14][4].
The idea. The IEA says that reaching national goals means adding or refurbishing over 80 million km of grids by 2040, and that new grid infrastructure often takes five to 15 years to plan, permit and complete, against one to five years for new renewables projects [14]. At least 3,000 GW of renewable projects wait in grid connection queues [14]. For households outside the grid, the World Bank says reaching 490 million people by 2030 needs more than 217,000 mini grids, but at the current pace only 44,800, serving 80 million people, will be built [4].
The limit. Permitting and build time: new grid takes five to 15 years, so it lags the generation that needs it [14].
What could unlock it. Solar mini-grids reach people the main grid has not [4]; the sources do not quantify how much faster permits could become.
PV Solar photovoltaicsHVDC HVDC linksV2G Demand response and vehicle-to-grid
as of 2026-11-23
Sources
- Solar mini grids could power half a billion people by 2030, if action is taken now World Bank, 2022
- Principles of High Voltage Transmission EE Power (Ahmed Sheikh), 2025
- University Physics Volume 2, section 9.3: Resistivity and Resistance OpenStax, Rice University, 2016
- Benchmarking Discom performance: highlights of the MoP's 14th Integrated Rating and Ranking Report Powerline, 2026
- Guidelines for computation of AT&C Losses Central Electricity Authority
- Electricity grids and secure energy transitions: executive summary IEA, 2023
- Rising component prices and supply chain pressures are hindering the development of transmission grid infrastructure IEA, 2025
- GTRI: India's power sector facing 30 percent shortage of CRGO steel SteelOrbis (reporting GTRI), 2024
- Lok Sabha unstarred question 1951: AT&C losses (reply of the Ministry of Power) Lok Sabha, Parliament of India, 2025