Material Insights · Understanding the Material World

Waste heat for drying, water and food: Levers

Held back most by

Economics

The heat is free and the physics allows it: a cubic metre of water needs about 627 kWh to evaporate (calculated) [11], and thermal desalination plants listed at 80.6 kWh of heat per cubic metre reuse the heat [3]. What decides use is whether a user's payback beats the usual two to three years and whether a user sits near the heat: Cadmus lists lack of a viable end use among the barriers [13]. This is judgement on thin evidence.

The six layers

Mathematics, science, engineering, production, economics, and resources and rules: what each gives, the idea in plain words, the limit (hard or soft) and how close today is, what could unlock it, and the maths behind it

Six layers make a technology possible, from the mathematics underneath to the resources and rules it needs at world scale. A hard limit comes from mathematics or nature and can only be sidestepped; a soft limit moves with effort, scale, money or policy.

  1. 1 Mathematics Hard limit

    Mathematics is the language of its physics

    What it gives. The heat sum that says how much warming a stream of waste heat can do.

    The idea. A physical law makes the uses work and mathematics counts the heat, so the role is language: the heat needed to warm water or air is mass times specific heat times temperature rise [10]. The BEE guide book says low-temperature waste heat may be useful in a supplementary way for preheating [12].

    The limit. The sum says how much heat a task needs, not whether a source of the right temperature is near it.

    What could unlock it. The BEE chapter's own heat sum uses flow, density, specific heat and temperature difference for gases [12].

    Show the maths Q = m c ΔT
    Q
    the heat needed, in joules
    m
    the mass of water, in kilograms
    c
    the specific heat: heat to warm 1 kg by 1 °C, 4,186 J for water
    ΔT
    the rise in temperature, in °C

    In plain words. To warm water you must give it heat. This sum says how much. A tank of water is a good place to put heat that is too cool to make steam.

    Worked example. 1 m³ (1,000 kg) of water warmed from 25 °C to 60 °C (both assumed): Q = 1,000 × 4,186 × 35 = 146.51, or 40.7 kWh (calculated), using water's specific heat from the table [10].

  2. 2 Science Hard limit

    What it gives. Latent heat: turning water into vapour takes a fixed, large amount of heat, whatever the source.

    The idea. Drying and distillation both evaporate water. It takes 2,256 kJ to evaporate each kilogram of water at 100 °C [11], which is about 627 kWh for a cubic metre (calculated). Multi-effect distillation and multi-stage flash plants are listed at 80.6 kWh of heat for each cubic metre of fresh water [3], about one eighth of that (calculated).

    The limit. No dryer or still can evaporate water for less than its latent heat unless the heat is used again; the gap between 627 and 80.6 kWh fits a plant that reuses the same heat several times (judgement) [11][3].

    What could unlock it. High-temperature heat pumps reach heat sink temperatures of 90 to 160 °C, suited especially to drying, pasteurising, sterilising, evaporation and distillation [14].

    MVR Industrial heat pumps and vapour recompression

    Show the maths Q = m Lv
    Q
    the heat needed to evaporate the water, in joules
    m
    the mass of water, in kilograms
    Lv
    the latent heat of vaporisation: heat per kilogram, 2,256 kJ for water at 100 °C

    In plain words. Drying means turning water into vapour. That takes a big lump of heat for every kilogram, much more than warming the water. You cannot dodge this. You can only use cheap heat for it, or use the same heat again and again.

    Worked example. 1,000 kg of water at 100 °C: Q = 1,000 × 2,256 kJ = 2,256,000 kJ, or 2,256 MJ, which is 626.7 kWh (calculated) [11]. The multi-effect plant's 80.6 kWh [3] is 626.7 ÷ 80.6 = 7.8 times smaller (calculated); the table's value is at 100 °C and the plant runs near 70 °C.

  3. 3 Engineering Soft limit

    What it gives. Driers, stills, greenhouse coils and chillers fed by heat that boilers would waste.

    The idea. Multi-effect distillation runs at 70 °C and multi-stage flash at 90 to 110 °C; the thermal plants also need electricity, 1.5 to 2.5 kWh a cubic metre for multi-effect and 2.5 to 3.5 for multi-stage flash, against 3.5 to 5.0 kWh of electricity a cubic metre for large reverse osmosis plants [3]. ORNL lists contaminants, corrosion from condensate, low efficiencies and long paybacks as barriers to low-temperature recovery [2].

    The limit. Heat cooler than the task needs cannot be used directly (judgement); BEE gives a rule of thumb that fluids below 120 °C, or better 150 °C, are the limit for waste heat recovery because of the risk of condensation of corrosive liquids [12].

    What could unlock it. High-temperature heat pumps reach sink temperatures of 90 to 160 °C [14].

  4. 4 Production Soft limit

    What it gives. Plants built beside a heat source, one at a time.

    The idea. Reverse osmosis accounts for 60% of global desalination capacity and multi-stage flash for 26.8% [3]; thermal desalination is a minority of the installed base.

    The limit. These are built case by case next to a heat source, so output is by project, not by factory (judgement); I found no Indian production figures.

    What could unlock it. The multi-stage flash process can be powered by waste or by-product heat [3].

  5. 5 Economics Soft limit Binds most today

    What it gives. Heat that costs nothing to a user who would otherwise buy fuel or electricity.

    The idea. Cadmus's paper says paybacks under two to three years are generally accepted, and lists long payback periods and lack of a viable end use among the barriers [13]. Thermal desalination uses 80.6 kWh of heat plus electricity per cubic metre, against 3.5 to 5.0 kWh of electricity for reverse osmosis [3].

    The limit. Thermal desalination only competes where the heat is nearly free (judgement, from the kWh figures [3]); a dryer used only in season earns less (judgement).

    What could unlock it. Free heat next to a user: the paper notes that some industrial facilities do not have use for low temperature heat [13].

    Show the maths A = r ÷ (1 - (1 + r)-n) × P
    A
    the yearly charge that repays the cost, in rupees
    r
    the yearly cost of capital, as a fraction
    n
    the years over which the cost is repaid
    P
    the installed cost of the dryer or plant, in rupees

    In plain words. Money borrowed for a machine has to be paid back with interest. The first part of the sum turns the price of the machine into an even yearly charge over its life. If the fuel saved each year is larger than that charge, the machine pays for itself.

    Worked example. P = Rs 1 crore (100 lakh), r = 12% and n = 15 years (all assumed). CRF = 0.12 ÷ (1 - 1.12-15) = 0.1468 (calculated) [16], so A = Rs 14.68 lakh a year (calculated). The value of the heat used must beat that.

  6. 6 Resources and rules Soft limit

    What it gives. A user for the heat at the same site as the source, and policy that rewards it.

    The idea. The Cadmus paper lists distance between source and sink and limited space as costs, and notes that some facilities have no use for low temperature heat [13]. The Carbon Credit Trading Scheme binds about 490 entities in seven sectors from 2025-26 [15].

    The limit. The heat user must sit next to the heat source (judgement, from the cited costs of distance) [13].

    What could unlock it. Industrial clusters and shared heat networks bring users to sources (judgement).

    Shr Shared and district heat reuseMVR Industrial heat pumps and vapour recompression

as of 2026-11-24

Sources

  1. Technology Assessment on Low-Temperature Waste Heat Recovery in Industry, ORNL/TM-2021/2150 (Thekdi, Nimbalkar et al.) Oak Ridge National Laboratory, 2021
  2. Water Desalination Using Renewable Energy, Technology Brief I12 IEA -ETSAP and IRENA, 2012
  3. Heat Transfer, Specific Heat, and Calorimetry (University Physics Volume 2, section 1.4) OpenStax, 2016
  4. Phase Changes (University Physics Volume 2, section 1.5, undated) OpenStax, 2026
  5. 8. Waste Heat Recovery (guide book chapter, undated) Bureau of Energy Efficiency, 2026
  6. Not Just Hot Air: Low-Cost Decarbonization through Heat Recovery (Zahlan and Talan, Cadmus), ACEEE Summer Study on Energy Efficiency in Industry ACEEE, 2021
  7. High Temperature Heat Pumps: Market Overview, State of the Art, Research Status, Refrigerants, and Application Potentials (Arpagaus, Bless, Uhlmann, Schiffmann, Bertsch), 17th International Refrigeration and Air Conditioning Conference, Purdue (conference paper) Purdue e-Pubs, 2018
  8. Compliance obligations under India's Carbon Credit Trading Scheme enter into force for seven sectors International Carbon Action Partnership (ICAP), 2026
  9. Equations and Variables in the ATB (2024) NREL, 2024