HVDC links: Evolution
Timeline
The milestones from first idea to today
| Year | Milestone |
|---|---|
| 1882 | Deprez and von Miller send direct current 57 km from Miesbach to Munich [1] |
| 1902 | Peter Cooper Hewitt invents the mercury-arc rectifier, around 1902 [3] |
| 1954 | The Gotland link, 20 MW at 100 kV over a 96 km subsea cable, becomes the first commercial HVDC link [2] |
| 1970 | Gotland is upgraded with the first thyristor valves, raising its voltage to 150 kV [2][3] |
| 1987 | Gotland becomes a bipole of 260 MW at plus and minus 150 kV [2] |
| 2019 | State Grid commissions the Changji to Guquan link in China, the first at 1,100 kV, 3,293 km long with a capacity of 12 GW [4] |
| 2025 | The IEA reports lead times for direct current cables beyond five years [5] |
as of 2026-11-12
Lineage
The technologies it came from and the ones that came from it
Works with- HVAC AC transmission Every HVDC link starts and ends in AC grids; Gotland joined the island's grid to mainland Sweden [2], and HVDC uses about one third less metal than AC for the same job [6].
- Cab Underground, submarine and superconducting cables Gotland used the first submarine HVDC cable, 96 km of mass-impregnated cable [2].
- PE Transformers and power electronics Thyristor valves replaced mercury-arc valves from 1970 [2][3].
as of 2026-11-12
Sources
- Gedenkstein Miesbach - München VDE (Verband der Elektrotechnik), Geschichte der Elektrotechnik
- Milestones:Gotland High Voltage Direct Current Link, 1954 IEEE, Engineering and Technology History Wiki (ETHW)
- A Short History of The Mercury-Arc Valve T&D World (Gene Wolf), 2017
- State Grid commissions new 1,100 kV power transmission line (China) Enerdata, Daily Energy News, 2019
- Building the Future Transmission Grid: executive summary IEA, 2025
- The Role of Critical Minerals in Clean Energy Transitions: Mineral requirements for clean energy transitions International Energy Agency