HVDC links: Technology advances

Ultra-high voltages, smarter converters and record subsea links

What this tab covers The newest technologies in service or close to adoption, what each improves, and how the main options compare.

The frontier is higher voltages and powers (UHVDC), voltage-source converters for offshore wind and weak grids, longer subsea links, and bulk procurement to secure factory slots.

Latest advances

±1,100 kV UHVDC in service · 2019

LCC link of 12 GW over 3,293 km from Xinjiang to eastern China12

Improves: Up to 40% lower losses than conventional systems, according to the converter supplier

Voltage-source converters (VSC) in service · 2023

IGBT-based modular multilevel converters that control active and reactive power independently6

Improves: Black-start capability and weak-grid support; 53 VSC projects existed in May 2023 and 102 more were planned to 2032

Very long subsea interconnectors in service · 2023

Viking Link, 765 km of land and subsea cable between the UK and Denmark8

Improves: Joins two markets across the North Sea; expected to save about 600,000 tonnes of CO2 in its first year

400 kV subsea link, Bay of Biscay being deployed · 2028

Two 1,000 MW HVDC links of about 400 km between Spain and France with four converter stations1617

Improves: Raises Spain to France exchange capacity from 2,800 to 5,000 MW

Framework procurement being deployed · 2025

National Grid reserved converter and cable factory capacity through multi-year frameworks9

Improves: About GBP 24.6 billion of converter and GBP 21.3 billion of cable work

Comparing the options

OptionEfficiencyCostCapacity or distanceMaturity
LCC HVDC overhead (±800 to ±1,100 kV)13About 3.5% per 1,000 km including converters (Xiangjiaba, calculated)Cheaper converters than VSC6,400 to 12,000 MW per linkmature
VSC HVDC (overhead or cable)4816About 0.8 to 1% per converter station plus line or cable lossesHigher converter cost than LCC1,000 to 1,400 MW per link in recent subsea projectsmature
HVAC overhead (765 kV)18Higher losses on long routesCheaper below about 250 to 400 milesAbout 2,400 MW natural loading per circuitmature
HVAC cable4Charging current uses up capacity on long cablesNo converters; HVDC cheaper beyond about 30 milesLimited to short routesmature

HVDC is the only practical choice for long subsea links and the cheapest for very long overhead routes. Brattle puts the break-even with AC at about 700 km for new build; converting an existing AC corridor to DC can pay beyond about 200 km, or wherever capacity must rise by more than 60%. MISO's range is 250 to 400 miles.

Sources

  1. The world's most powerful transmission system facilitated by Hitachi ABB Power Grids Hitachi Energy, 2020
  2. China's SGCC commissions world's first ±1,100 kV UHVDC project Power Line Magazine, 2019
  3. Xiangjiaba - Shanghai (case study) Hitachi Energy, 2024
  4. Overview of HVDC Technologies and EPRI's HVDC Research (R. Adapa, presentation to ERCOT) EPRI / ERCOT, 2023
  5. HVDC Transmission: Multi-Value Planning Considerations and Experience The Brattle Group (for MISO), 2023
  6. National Grid announces commercial operations of Viking Link, the world's longest land and subsea interconnector National Grid, 2023
  7. National Grid awards HVDC supply chain framework contracts National Grid, 2025
  8. Hitachi Energy wins order for first subsea electricity interconnection between France and Spain Renewable Energy Magazine, 2023
  9. EIB supports with EUR 1.6 bn the strategic Bay of Biscay electricity interconnection between Spain and France European Investment Bank, 2025
  10. Discussion of EHV and HVDC (M. Tackett, MISO, presentation to ERCOT) MISO / ERCOT, 2023