HVDC links: Unit economics

Costly stations, cheap kilometres: the economics of distance

What this tab covers What it costs to move a unit of energy this way: capital and operating costs, tariffs, utilisation and how it compares with the alternatives.

HVDC has high fixed costs at the converter stations but cheaper lines per km, so its cost per MWh falls with distance and utilisation. Chinese UHVDC moves power 1,000 km for roughly USD 2 per MWh in capital recovery; European subsea links cost far more per MW.

Key costs

MeasureValueNote
Changji to Guquan ±1,100 kV investment40.7 CNY billion23,293 km, 12 GW; about CNY 3.4 billion per GW (calculated)
Cost to move 1 MWh 1,000 km, Changji to GuquanAbout 2.2 USD/MWh2Calculated: capital recovery at 8% over 40 years, 66 TWh a year, CNY 7.1 per USD; excludes operating cost and losses
Viking Link (UK to Denmark)1.7 GBP billion81.4 GW, 765 km; about GBP 1.2 million per MW and GBP 2.2 million per km (calculated); 2023
Great Sea Interconnector budget1.9 EUR billion13About 1,200 km subsea; about EUR 1.6 million per km (calculated); 2026
Break-even distance versus ACAbout 300 (overhead) and 30 (cable) miles46EPRI, 2023; Brattle gives about 700 km for new overhead build

Where the money goes

ItemShare or amount
National Grid HVDC frameworks: convertersAbout GBP 24.6 billion, about 42% (calculated)9
National Grid HVDC frameworks: cablesAbout GBP 21.3 billion, about 36% (calculated)9
National Grid HVDC frameworks: converter and onshore cable civil worksAbout GBP 12.8 billion, about 22% (calculated)7

The framework split shows that converters and cables each cost more than the civil works around them. Subsea links cost more per km than overhead lines because of cable manufacture and specialist installation vessels, and Chinese overhead UHVDC is far cheaper per MW-km than European subsea projects.

Alternatives include shipping or piping fuel to a power station near the load, which avoids the line but adds conversion losses, and building generation locally. Merchant schemes such as Xlinks depend on long-term revenue guarantees; regulated interconnectors are paid from congestion income or tariffs.

Sources

  1. China's SGCC commissions world's first ±1,100 kV UHVDC project Power Line Magazine, 2019
  2. Overview of HVDC Technologies and EPRI's HVDC Research (R. Adapa, presentation to ERCOT) EPRI / ERCOT, 2023
  3. HVDC Transmission: Multi-Value Planning Considerations and Experience The Brattle Group (for MISO), 2023
  4. National Grid names eight for GBP 12bn HVDC framework The Construction Index, 2025
  5. National Grid announces commercial operations of Viking Link, the world's longest land and subsea interconnector National Grid, 2023
  6. National Grid awards HVDC supply chain framework contracts National Grid, 2025
  7. EU-backed electricity link to Cyprus stalls amid regional tensions Euronews, 2026