Output and value

World output and its value, with year and source

MeasureValueUnitYearSource
Wind turbines mechanically installed worldwide28,395turbines2025[6]
Capacity of the turbines mechanically installed worldwide (165 GW grid connected, 13 GW awaiting commissioning)178GW2025[6]
Average rating of a turbine installed in 2025 (calculated: 178 GW / 28,395)6.3MW2025[6]
Wind turbines mechanically installed worldwide23,098turbines2024[7]
Capacity installed by turbine makers127GW2024[7]
BloombergNEF's count of wind capacity added (a different method from GWEC)169GW2025[8]
Vestas turbines delivered14,537MW2025[10]
Vestas revenue18.8EUR billion2025[10]

as of 2026-11-13

Where it is made

Country shares of world output

CountryShareMeasureYearSource
China59Turbines installed in 2025 by the top five Chinese makers (105.0 GW of 178 GW, calculated); a maker's headquarters, not a factory count2025[6]
Denmark7.2Vestas turbines installed outside mainland China in 2025 (12.9 GW), as a share of 178 GW, calculated2025[6]
Germany4.3Nordex Group installed outside mainland China in 2025 (7.7 GW), calculated2025[6]
United States of America3.3GE Vernova installed outside mainland China in 2025 (5.8 GW), calculated2025[6]

as of 2026-11-13

Main companies

The largest makers and their shares

CompanyCountryShareMeasureYearSource
GoldwindChina16.729.7 GW installed in 2025 (share of 178 GW, calculated)2025[6]
EnvisionChina12.221.8 GW installed in 2025 (share of 178 GW, calculated)2025[6]
WindeyChina11.119.8 GW installed in 2025 (share of 178 GW, calculated)2025[6]
MingyangChina10.418.6 GW installed in 2025 (share of 178 GW, calculated)2025[6]
SANYChina8.515.1 GW installed in 2025 (share of 178 GW, calculated)2025[6]
VestasDenmark7.212.9 GW installed in 2025 (share of 178 GW, calculated); counted outside mainland China2025[6]
SuzlonIndia– Record 2,456 MW delivered in the financial year 2025-26, up from 1,550 MW; deliveries are not a market share2026[20]

as of 2026-11-13

Supply chains of the main makers

For the top three to five producing countries and India: share, where inputs and components come from, main makers and how variants differ

CountryShareInputs fromMakersHow variants differYearSource
China59Chinese makers' installs were 93% at home in 2025 (99% in 2024); China also mines about 69% of world rare earths and makes 94% of sintered magnets, the inputs of direct-drive generators [8][24][25]Goldwind, Envision, Windey, Mingyang, SANY [6]Dongfang installed a 26 MW offshore turbine in 2025 (company claim) [13]2025[6][8]
Denmark7.2Not reported in the sources foundVestas, largest maker of commissioned projects outside mainland China [8]Vestas delivered 1,977 MW offshore of 14,537 MW in 2025 [10]2025[6][10]
Germany4.3Not reported in the sources foundNordex Group; Siemens Energy's wind unit (Siemens Gamesa) topped the offshore market in 2025 [8]Siemens Gamesa installed 5.4 GW outside mainland China in 2025 [6]2025[6][8]
United States of America3.3Not reported in the sources foundGE VernovaNot reported2025[6]
India– Blades, towers, gearboxes, generators and special bearings must come from approved domestic makers under ALMM (Wind) from 31 July 2025 [19]; about 70 to 80% indigenisation [17]About 14 companies; Suzlon delivered 2,456 MW in FY26; Adani's 5.2 MW MWL-160 and Venwind Refex's 5.3 MW GWH182 are the largest models [17][20][18]No offshore installation yet [17]2026[19][17][20][18]

as of 2026-11-13

Industries that make it

The industries and kinds of firm that make it

Made by

as of 2026-11-13

Critical inputs

Inputs whose supply is concentrated, listed as critical or under export controls

InputWhyConcentrationListingYearSource
Rare earthsNeodymium, praseodymium, dysprosium and terbium in the magnets of direct-drive and hybrid generators; 180 kg of neodymium per MW in the JRC's direct-drive caseChina mined about 69% of world rare earths in 2025 (calculated) and made 94% of sintered magnets in 2024China put seven heavy rare earths and related magnets under export control in April 2025; wider October 2025 controls are suspended to 10 January 20272025[4][24][25][28][29]

as of 2026-11-13

Rules and standards

Labels, efficiency and emission standards, producer responsibility, bans and tariffs

RulePlaceYearWhat it doesSource
ALMM (Wind), formerly the Revised List of Models and ManufacturersIndia2025In force from 31 July 2025: key components (blades, towers, gearboxes, generators, special bearings) must come from approved domestic suppliers; projects bid out before that date are exempt if commissioned within three years; new makers and models get an exemption for 800 MW over two years; wind turbine data must be stored in India [19][19]
Foreign Subsidies Regulation inquiry into Chinese wind turbine suppliersEuropean Union2024The Commission opened an inquiry on 9 April 2024 into Chinese turbine suppliers, first in Bulgaria, France, Greece, Romania and Spain; WindEurope cited offers at up to 50% lower prices [22][22]
Landfill bans on decommissioned bladesAustria, Finland, Germany, Netherlands2021Four countries already banned landfilling; WindEurope asked the Commission for a Europe-wide ban and expects around 25,000 t of blades a year by 2025 and 52,000 t by 2030 [21][21]
Chinese export controls on seven heavy rare earths and magnets (Announcement No. 18)China2025Licences needed to export samarium, gadolinium, terbium, dysprosium, lutetium, scandium and yttrium and related items from April 2025; still in force [28][29][28][29]

as of 2026-11-13

India

India's output, trade, makers and rules in a short paragraph

India had 59.2 GW of wind at the end of September 2026 [16] and added a record 6.05 GW in 2025-26 [31], third in the world in 2025 with 6.3 GW [5]. Annual turbine manufacturing capacity is about 18,000 MW [17]. Since 31 July 2025 ALMM (Wind) requires blades, towers, gearboxes, generators and bearings from approved domestic makers [19]. Trade data are loaded separately.

as of 2026-11-13

Trade

World exports, the top exporters and importers and India, from UN Comtrade by HS code (worked out by the site)

FlowValueUnitVolumeUnitYearSource
World exports6.63USD billion571.4thousand tonnes2024UN Comtrade, HS 8502.31
Average export value (calculated)11.6USD per kg– – 2024UN Comtrade, HS 8502.31
Exporter: Denmark (36.0% of world exports)2.39USD billion– – 2024UN Comtrade, HS 8502.31
Exporter: Germany (30.0% of world exports)1.99USD billion230.5thousand tonnes2024UN Comtrade, HS 8502.31
Exporter: China (18.0% of world exports)1.19USD billion236.2thousand tonnes2024UN Comtrade, HS 8502.31
Exporter: France (6.0% of world exports)0.4USD billion30thousand tonnes2024UN Comtrade, HS 8502.31
Exporter: Spain (4.5% of world exports)0.3USD billion33.7thousand tonnes2024UN Comtrade, HS 8502.31
India exports (rank 6, 3.3% of world)0.22USD billion23.2thousand tonnes2024UN Comtrade, HS 8502.31
India imports (rank 37, 0.2% of world)0.01USD billion1.1thousand tonnes2024UN Comtrade, HS 8502.31
Importer: United Kingdom (10.7% of world imports)0.63USD billion57.2thousand tonnes2024UN Comtrade, HS 8502.31
Importer: Türkiye (10.2% of world imports)0.61USD billion61.6thousand tonnes2024UN Comtrade, HS 8502.31
Importer: South Africa (8.2% of world imports)0.49USD billion– – 2024UN Comtrade, HS 8502.31

Worked out from data

Sources

  1. Raw materials demand for wind and solar PV technologies in the transition towards a decarbonised energy system (Carrara et al., EUR 30095 EN), Table 4 European Commission Joint Research Centre, 2020
  2. Global wind installations rise record 40% as industry charts way out of energy crisis Global Wind Energy Council, 2026
  3. Global Wind Installations Hit Record 178 GW in 2025, Five Manufacturers Cross 100 GW Cumulative Mark Baltic Wind, 2026
  4. Wind Turbine Suppliers deliver new record volume Global Wind Energy Council, 2025
  5. Chinese Turbine Suppliers Seize the Spotlight as Global Wind Power Installations Hit All-Time High, BloombergNEF Report Shows BloombergNEF, 2026
  6. Vestas Ends 2025 with All-Time High Revenue and EUR 10.1 Billion Offshore Wind Turbine Order Backlog offshoreWIND.biz, 2026
  7. Offshore Wind Turbines in 2025: China Continues Leading in Single-Unit Capacity, Vestas's 15 MW Turbine Installed at Offshore Wind Farms offshoreWIND.biz, 2026
  8. India's Installed Wind Power Capacity Reaches 59.2 GW With 11% Year-On-Year Growth In September 2026 SolarQuarter, 2026
  9. Strong Tailwinds: Sector witnesses rapid progress despite setback in offshore Renewable Watch, 2026
  10. Powering Up: Shift towards higher capacity turbines Renewable Watch, 2026
  11. Domestic push: India mandates local supply chains and data centres for wind turbines Down To Earth, 2025
  12. Top Wind Turbine Companies in India 2026: Suzlon Leads as Inox, Envision, Adani and GE Vernova Scale Up GreentechLead, 2026
  13. Wind industry calls for Europe-wide ban on landfilling turbine blades WindEurope, 2021
  14. EU starts investigation into Chinese wind turbines under new Foreign Subsidies Regulation WindEurope, 2024
  15. Mineral Commodity Summaries 2026: Rare Earths US Geological Survey, 2026
  16. Rare Earth Elements: executive summary International Energy Agency, 2026
  17. China Suspends Export Controls on Certain Critical Minerals and Related Items Pillsbury Winthrop Shaw Pittman LLP, 2025
  18. China extends rare earth export suspension to January 2027 S&P Global, 2026
  19. India Adds 6.05 GW Wind Power Capacity in FY26, Total Installed Capacity Crosses 56 GW Energetica India, 2026