HVDC links: Levers

Held back most by

Resources and rules

The technology is mature and ±800 kV, 6,000 MW links are being built in India [17][18], but India lost 300 GWh of clean power to transmission constraints in the first quarter of 2026, and one in four major schemes is a year or more late [19]. Land acquisition and right of way are named as among the most significant challenges [18], so permission and delivery, not the converter, set the pace.

The six layers

Mathematics, science, engineering, production, economics, and resources and rules: what each gives, the idea in plain words, the limit (hard or soft) and how close today is, what could unlock it, and the maths behind it

Six layers make a technology possible, from the mathematics underneath to the resources and rules it needs at world scale. A hard limit comes from mathematics or nature and can only be sidestepped; a soft limit moves with effort, scale, money or policy.

  1. 1 Mathematics Hard limit

    Mathematics is the language of its physics

    What it gives. The loss law P = I²R tells a designer what a wire costs in heat, and why long lines run at very high voltage [10].

    The idea. A physical law, Joule heating, does the work and mathematics only describes it, so the role is language. The power lost in a line is the square of the current times the resistance [10]. For the same power, a higher voltage means a smaller current, so a 50-fold rise in voltage (240 V to 12 kV in the source's example) cuts the loss by a factor of 2,500 [10] (calculated).

    The limit. Loss grows with the square of the current, so at fixed power it falls with the square of the voltage; a line can never be lossless while it has resistance [10].

    What could unlock it. Raising the voltage is the route: thyristor converters can now work at ±1,100 kV with an overhead line [13].

    Show the maths Ploss = I2 × R, I = P ÷ V
    Ploss
    the power lost as heat in the line, in watts
    I
    the current in the line, in amps
    R
    the resistance of the line, in ohms
    P
    the power sent, in watts
    V
    the voltage of the line, in volts

    In plain words. A wire warms up when current goes through it, and the warming is wasted power. Double the current and you get four times the heat. So send the same power at a higher voltage and a smaller current, and the loss shrinks fast. That is why the long links run at hundreds of thousands of volts.

    Worked example. The loss formula is the source's [10], and its example sends the same power at 12 kV and 2.0 A or at 240 V and 100 A [10]. Take the Khavda to Nagpur ratings, 6,000 MW at ±800 kV [17], so 1,600 kV between the two poles, and assume a loop resistance of 12 Ω. Then I = 6,000 MW ÷ 1,600 kV = 3,750 A, and Ploss = 3,750² × 12 = 169 MW, or 2.8% of the power (calculated). At half the voltage the current doubles and the loss is four times as much, 11% (calculated). The 12 Ω is an assumption, not a published figure.

  2. 2 Science Hard limit

    What it gives. A direct current charges a cable once and then just flows, so the whole cable is free to carry power, which is the effect that lets HVDC span long distances [11].

    The idea. An alternating-current cable acts like a capacitor, and most of its current can go on charging and discharging that capacitance, using up its thermal capacity [11]. A capacitor's current grows with voltage, frequency and capacitance [12], so a high-voltage AC cable has a maximum practical length of about 50 to 100 km [11].

    The limit. Cable capacitance: the charging current of an AC cable grows with its length, so beyond about 50 to 100 km little room is left for useful power [11][12].

    What could unlock it. Direct current has no repeated charging, so it sidesteps the limit; the price is two converter stations, and HVDC breaks even with AC beyond about 300 miles for overhead lines and about 30 miles for underground cables [13].

    Show the maths Ic = 2π × f × C × E0
    Ic
    the charging current of the cable, in amps (amps each km when C is given each km)
    f
    the frequency of the grid, in hertz
    C
    the capacitance of one core to earth, in farads (or farads each km)
    E0
    the voltage from a conductor to earth, in volts

    In plain words. A cable is two metal surfaces with insulation between them, which makes it a store of charge. With alternating current, the voltage reverses 100 times a second on a 50 hertz grid, so the cable is filled and emptied again and again. That sloshing current takes up room in the cable that useful power could have used. The longer the cable, the more capacitance, so the more room it takes.

    Worked example. The textbook gives a capacitor's reactance as XC = 1 ÷ (2π f C) and its current as I = V ÷ XC[12], so Ic = 2π × f × C × E0 (calculated). For the 420 kV, 50 Hz three-core cable in a published study, with 190 nF each km and a rated current of 945 A [22]: E0 = 420 kV ÷ √3 = 242 kV, so Ic = 2π × 50 × 0.19 × 10-6 × 242,000 = 14.5 A each km (calculated). Fed from one end, charging alone would use the whole 945 A after about 65 km (calculated), inside the 50 to 100 km in [11].

  3. 3 Engineering Soft limit

    What it gives. Converter stations turn AC to DC and back, and the rest is a line or cable; in 2023 EPRI listed line-commutated links to ±1,100 kV and 12,000 MW on a single bipole [13].

    The idea. A converter station loses about 0.8% of the power at rated load for the older thyristor type and 0.8 to 1.0% for the newer multilevel voltage-source type [13]. The Xiangjiaba to Shanghai link, 1,980 km at ±800 kV and rated at 6,400 MW, has 7% total losses against 10% on a conventional 500 kV DC line [14].

    The limit. Voltage-source converters and cables reach lower voltages and ratings than thyristor links: up to ±600 kV overhead and ±525 kV on cable, typically 1,200 MW to as high as 3,000 MW [13].

    What could unlock it. Raising voltage and rating per converter is the engineering route; the voltage-source type is the one that suits subsea and multi-terminal links [13].

  4. 4 Production Soft limit

    What it gives. Each link needs two converter stations, transformers and hundreds of kilometres of line or cable, all built to order [15][18].

    The idea. The IEA reports that procurement takes two to three years for cables and up to four years for large power transformers, and that waiting times for direct current cables extend beyond five years; cable costs have nearly doubled since 2019 [15]. In India a consortium led by Hitachi Energy India and BHEL won a major HVDC contract for the Khavda link in 2024, and a Hitachi Energy and BHEL consortium won Bhadla to Fatehpur in mid-2025 [18].

    The limit. Lead times for transformers, cables and converter valves, set by a few makers, limit how fast links can be started [15].

    What could unlock it. Local manufacture with a lead supplier, as in the Hitachi Energy and BHEL partnership, shortens the wait for converters [18]; overhead lines need no DC cable.

  5. 5 Economics Soft limit

    What it gives. Khavda to Nagpur, 6,000 MW, ±800 kV and about 1,200 km, was estimated at Rs 24,819 crore and was the first HVDC project tendered by tariff-based competitive bidding [17].

    The idea. That is about Rs 4.1 crore a MW (calculated). Regulated transmission earns a 15.00% return on equity for new projects from April 2024 [21]. HVDC beats AC only beyond a break-even distance, over 300 miles for overhead lines [13]; one study of very long subsea links put it at about 180 km on capital cost for one AC cable and 240 to 400 km on total net present cost for two others [22].

    The limit. Utilisation and cost of capital: the line is paid for up front, so a link that sits part empty, or a high interest rate, raises the cost of each unit it carries [18][19].

    What could unlock it. Competitive bidding sets the return by the bid [17], and a high load factor lowers the cost per unit; lines held up by delay earn nothing while the power they were to carry is lost [19].

    Show the maths CRF = r ÷ (1 - (1 + r)-n), cost per kWh = capex × CRF ÷ kWh a year
    CRF
    the capital recovery factor: the share of the up-front cost paid back each year
    r
    the yearly cost of capital, as a fraction
    n
    the number of years the link earns
    capex
    the up-front cost of the link, in rupees
    kWh a year
    the energy the link carries each year

    In plain words. Building a link costs a lot at the start and has no fuel to buy afterwards. You pay the loan back over the life of the link, and the yearly payment divided by the units carried is the charge per unit. A busy link spreads its cost over more units, so it charges less for each.

    Worked example. Capex Rs 24,819 crore [17], n = 35 years, the useful life for transmission lines including HVDC in the regulations [21], and, as assumptions, a load of 60% and a cost of capital of 8% or 12% (the 15% in the regulation is a return on equity only). At 8%, CRF = 0.0858, so the yearly charge is Rs 2,130 crore; 6,000 MW × 8,760 h × 0.60 = 31.5 TWh, so the capital charge is about Rs 0.68 a kWh. At 12%, CRF = 0.1223 and it is about Rs 0.96 a kWh, 43% higher (calculated) [20].

  6. 6 Resources and rules Soft limit Binds most today

    What it gives. A link needs a continuous strip of land, state clearances and a grid that can take its power at both ends [18][19].

    The idea. The government plans to raise inter-regional transmission capacity from about 119 GW to 143 GW by 2027 and 168 GW by 2032, with 190,000 circuit km added, an investment of over Rs 9.15 lakh crore [16]. Ember counts 300 GWh of clean power lost to transmission constraints in the first quarter of 2026, and says one in four major schemes is already a year or more behind schedule [19].

    The limit. Land acquisition remains one of the most significant challenges, with delays from compensation disputes and right-of-way constraints [18].

    What could unlock it. Time lost on land and clearances is the target: the IEA says permitting remains the primary cause of delays in transmission projects [5].

    Show the maths N = ΔC ÷ Plink
    N
    the number of links needed
    ΔC
    the extra transfer capacity wanted, in megawatts
    Plink
    the rating of one link, in megawatts

    In plain words. If a plan says the country needs a certain amount of extra transfer capacity, divide by the size of one link to see how many links that is. It shows the scale of the building job.

    Worked example. The plan raises inter-regional capacity from about 119 GW to 168 GW [16], or 49 GW (calculated). As an assumption, taking all of it as 6,000 MW HVDC links like the Khavda link [17] (in practice much will be AC), N = 49,000 ÷ 6,000 = about 8 links (calculated), an upper bound for HVDC.

as of 2026-11-23

Sources

  1. Building the Future Transmission Grid: executive summary IEA, 2025
  2. 15.6 Transformers (University Physics Volume 2) OpenStax
  3. HVDC special report: Why HVDC? (ABB Review) ABB
  4. 23.11 Reactance, Inductive and Capacitive (College Physics 2e) OpenStax, Rice University
  5. Overview of HVDC Technologies and EPRI's HVDC Research (R. Adapa, presentation to ERCOT) EPRI / ERCOT, 2023
  6. Xiangjiaba - Shanghai (customer story) Hitachi Energy
  7. Rising component prices and supply chain pressures are hindering the development of transmission grid infrastructure IEA, 2025
  8. Centre targets Rs 9.15 lakh crore investment opportunity in transmission sector by 2032 Business Today, 2024
  9. POWERGRID acquires TBCB route's first HVDC project, Khavda VA Power Transmission Zee Business, 2024
  10. Modernising the Grid: Technology trends shaping the transmission segment Power Line, 2025
  11. India lost 300 million units of renewable energy owing to transmission constraints in Q1 2026 Ember, 2026
  12. Simple levelized cost of energy (LCOE) calculator documentation National Laboratory of the Rockies (formerly NREL), US Department of Energy, 2026
  13. CERC (Terms and Conditions of Tariff) Regulations, 2024 Central Electricity Regulatory Commission, 2024
  14. Very long distance connection of gigawatt-size offshore wind farms: extra high-voltage AC versus high-voltage DC cost comparison (Lauria, Schembari, Palone and Maccioni), IET Renewable Power Generation Sapienza University of Rome (IRIS repository), 2016